AZIO Atlas One Plans Off-Grid Texas Data Center
AZIO AI Holdings says its Live Oak County campus will run fully off the ERCOT grid as Texas tightens data center interconnection rules.
Updated on Nov. 10, 2026 in Data Centers

Live Poll
Should data centers have to pay all their own electricity infrastructure costs?
AZIO AI Holdings confirmed that Atlas One, the first Project Atlas campus in Live Oak County, Texas, is designed to run fully off the ERCOT grid. The announcement comes as Texas implements Senate Bill 6 and new PUCT rules tightening data center grid interconnection requirements.
Why it matters
Texas is weighing roughly 474 gigawatts of requests to connect to ERCOT, about 90 percent of them from data centers, straining the state's grid. The off-grid design offers a model for how large computing loads could avoid adding to that strain.
ERCOT is weighing roughly 474 gigawatts of connection requests, about 90 percent from data centers, and Senate Bill 6 sets new standards for loads of 75 megawatts and up. Atlas One's planned Phase One is 11 MW, anchored by a 10-megawatt hosting agreement at $150 per kilowatt per month, with no capacity energized yet.
The players
AZIO AI Holdings
AZIO AI Holdings is the company behind Project Atlas and its Atlas One campus in Live Oak County.
ERCOT
The Electric Reliability Council of Texas operates the grid serving most of the state and is reviewing data center interconnection requests.
Public Utility Commission of Texas (PUCT)
The PUCT is the state agency regulating electric utilities and implementing new rules for data center grid connections.
The details
Under the Project Atlas plan, power is generated on site from natural gas next to the compute it serves. Generation for each phase will require its own air authorization before construction, and the planned 11 MW Phase One is expected to be built in practical blocks of work.
Timeline
August 2026: Governor ordered a verification audit before data centers advance through ERCOT interconnection, and ERCOT paused its first "Batch Zero" large-load study.
Nov. 5, 2026: ERCOT update showed verification still under way.
Dec. 10, 2026: ERCOT's verification report is due to the PUCT.
Roadmap
Atlas One arrives as Texas implements Senate Bill 6, which set new standards for loads of 75 megawatts and up. The off-grid design shows one way large data centers may respond as the state tightens how they connect to ERCOT.
Texas electricity customers could see grid costs shift as data centers are required to pay for their own electric infrastructure under the governor's directive. Residents near planned campuses may also see new gas generation approved through individual air permits.
The takeaway
Off-grid power is becoming a practical route for large computing loads in Texas as interconnection standards tighten. Watch the December ERCOT verification report to see how quickly other projects can follow.
What happens next
ERCOT's verification report is due to the PUCT on Dec. 10, 2026, which will indicate whether data centers can advance through interconnection.
Further reading
For more on the grid pressures behind this story, see Data Centers coverage.
More information
Review the company's SEC filings (Form 10-K and 10-Q) for primary disclosures on Project Atlas.
Source note: This article includes information reported by The Manila times.
Live Poll
Should data centers have to pay all their own electricity infrastructure costs?









