Council Member Pushes to Remove Double Utility Poles
Charleston Council member Leslie Skardon is pressing telecom companies to move wires so 196 double wood poles on James Island can come down.
Updated on Nov. 17, 2026 in Industry

Live Poll
Should Charleston require utility companies to move their wires within 90 days?
Charleston City Council member Leslie Skardon is pushing to remove double wood utility poles on James Island, where old poles remain standing beside replacements. Dominion Energy has already removed 101 such poles, but 196 more cannot come down until telecommunication companies transfer their wires.
Why it matters
Double wood utility poles pose safety risks, and their removal depends on seven telecommunication companies moving their wires in sequence. Skardon is seeking a city ordinance requiring wire transfers within 90 days, modeled on a similar ordinance Beaufort passed in 2024.
Dominion Energy removed 101 double wood poles in five weeks this summer, with 21 more ready to come down. Another 196 poles remain blocked until seven telecommunication companies, including AT&T, Comcast and Spectrum, transfer their wires.
The players
Leslie Skardon
Skardon is a Charleston City Council member representing District 12, which covers parts of central and southern James Island.
Dominion Energy
Dominion Energy is a major regional electric utility serving the Carolinas and Virginia.
The details
Skardon began sending letters to all seven telecom companies in May and has followed up roughly every two weeks since. Each provider must remove and reattach its wires in order based on its position on the poles, which has slowed the work.
Timeline
Summer 2026: Dominion Energy removes 101 double wood poles over five weeks.
May 2026: Skardon begins sending letters to seven telecommunication companies.
2024: Beaufort passes a similar ordinance that Skardon hopes to replicate.
Nov. 8, 2026: Skardon posts about the initiative on Facebook.
Industry Context
Charleston's effort follows the template Beaufort adopted in 2024, which required telecom providers to transfer wires within a fixed window after new poles go up. Skardon is seeking a comparable 90-day deadline for James Island.
Residents on James Island may see utility poles come down once telecom companies move their wires, reducing the safety risks that double poles present. Until then, the 196 blocked poles remain in place.
The takeaway
Stalled utility work often depends on coordination among multiple private companies, so local pressure and clear deadlines can matter. Watch for whether Charleston adopts an ordinance with a firm wire-transfer timeline.
Further reading
For more on local infrastructure, browse Utilities coverage across the Charleston area.
Source note: This article includes information reported by Post and Courier.