DOE Approves $23.5B Savannah River Plutonium Plant
The Department of Energy approved the cost baseline and full construction for a plutonium-pit facility at the Savannah River Site.
Updated on Nov. 23, 2026 in Science

On Oct. 15, the Department of Energy approved a $23.5 billion cost baseline and full construction approval for the Savannah River Plutonium Processing Facility. The project converts the unfinished shell of the abandoned MOX megaproject into a plant designed to manufacture at least 50 plutonium pits annually.
Why it matters
The approved figure is more than double the high end of DOE's 2021 preliminary range of $6.9 billion to $11.1 billion, underscoring the scale of cost growth in the project. Plutonium pits are core components of the nation's nuclear weapons, so the plant's timeline and budget bear directly on national security infrastructure in South Carolina.
The approved $23.5 billion baseline is more than double the high end of DOE's 2021 preliminary range of $6.9 billion to $11.1 billion. The Main Process Building's performance baseline was set at 60% design maturity rather than the 90% typically required by DOE, leaving open how much design work remains unfinished.
The players
Department of Energy
The federal department responsible for the nation's nuclear weapons complex and the oversight of the Savannah River Site project's budget and approvals.
National Nuclear Security Administration
The semi-autonomous agency within the Department of Energy that manages the nation's nuclear weapons program and confirmed the $23.5 billion project figure.
Fluor
The engineering and construction contractor that has issued 243 of 320 glovebox fabrication subcontracts for the plutonium plant project.
The details
Construction began on the former MOX shell in 2007 with a 2016 completion target, and DOE ended that contract in 2018 after the milestone was missed. Site crews have stripped the structure of HVAC ducts, piping, conduits, pumps, tanks, gloveboxes and wall coatings, and NNSA has authorized 10 early procurement and site-preparation packages totaling about $3.1 billion.
Timeline
2007: MOX construction started at the Savannah River Site.
2016: Original MOX completion target.
2018: DOE ended the MOX contract after missing the 2016 milestone.
2021: DOE issued a preliminary cost range of $6.9 billion to $11.1 billion.
Oct. 15, 2026: DOE approved the cost baseline and full construction; the project is scheduled for completion in December 2038.
Roadmap
The plant converts the unfinished shell of the abandoned MOX megaproject, which began construction in 2007 and was scrapped in 2018 after missing its 2016 completion target. The new project's approved $23.5 billion cost is more than double DOE's 2021 preliminary range, extending a pattern of cost growth at the Savannah River Site.
For South Carolina residents, the plant means roughly 3,000 more workers are expected at peak construction, bringing employment and spending to the Savannah River area. The project's cost and timeline will shape local jobs and regional budgets through 2038.
The takeaway
The plant's trajectory shows how an abandoned federal project can be repurposed, but also how far cost estimates can drift when design maturity is set below standard thresholds. Readers tracking national security infrastructure should watch whether the 2038 completion date holds as the budget grows.