Crews Begin Tearing Down Syracuse's I-81

Contractors have started removing the elevated Interstate 81 in downtown Syracuse, beginning with the north-end ramp to I-690 east.

Updated on Nov. 23, 2026 in Industry

Crews Begin Tearing Down Syracuse's I-81

Live Poll

Do you support tearing down urban elevated highways in your city?

New York state contractors have started removing the elevated Interstate 81 in downtown Syracuse, after the state officially closed the ramp from I-81 north to I-690 east last week. The work targets the north end of the 1.4-mile elevated highway along Almond Street.

Why it matters

The demolition reshapes the downtown Syracuse landscape and affects residents living closer to the highway. The state has committed to monitoring noise and air quality and to containing old paint dust that likely contains lead.

The first 750-foot ramp, standing 20 feet high with eight piers and one abutment, is the initial segment of a 1.4-mile elevated highway. The southbound I-690 west ramp, 50 feet at its tallest, carries 17 piers and two abutments, and the source does not give the project's total cost or completion date.

The players

New York State

New York State is the state government overseeing the removal of the elevated Interstate 81 in Syracuse.

The details

Contractors are removing old paint under a Class B containment process, using certified specialists with vacuum-shrouded tools to keep particles out of the air. Crews will cut channels in the concrete deck and rebar, then peel back slabs about 8 feet wide and 3 feet long, fold and stack them, and haul them away. A large cloth tarp has been hung under the bridge near Water Street.

Timeline

  1. Last week: State officially closed the I-81 north to I-690 east ramp.

  2. About six weeks after demolition begins: Removal of the first 750-foot stretch is expected to be complete.

Construction Context

The state has made public promises to monitor noise and air quality and to contain old paint dust that likely contains lead during the removal. The demolition is now testing whether those commitments hold as the work moves south toward residential apartments.

Residents near Almond Street and Water Street should expect ongoing demolition work as crews move south. Demolition will move closer to residential apartments as the work proceeds.

The takeaway

As demolition moves closer to Syracuse homes, the state's commitments on noise, air quality, and lead-dust containment will be tested in practice. Residents can track how those promises are kept as the first 750-foot stretch comes down over roughly six weeks.

Further reading

Explore more Syracuse construction coverage for context on the highway's removal.

Source note: This article includes information reported by Syracuse.