LS Cable Supplies Cables for New York Grid Project

LS Cable & System will provide roughly 700 billion Korean won of 345 kV cables for the Propel NY Energy transmission project.

Updated on Nov. 23, 2026 in Utilities

Empty wooden cable spool beside an open trench with a black high-voltage cable laid along its floor on a gravel yard under overcast light.
LS Cable & System will supply roughly 700 billion Korean won of 345 kV cables for New York's Propel NY Energy grid expansion, which has begun construction after state approval. AI Illustration. Upload story photo >

Live Poll

Do you expect your electricity bills to rise as New York expands its power grid?

LS Cable & System will supply approximately 700 billion Korean won of 345 kV underground and submarine cables for the Propel NY Energy project, which is building a grid expansion of about 145 km. Construction has begun after New York state authorities approved the implementation plan.

Why it matters

The project is intended to expand transmission capacity, stabilize power supply and integrate offshore wind into the grid. Demand for large-scale domestic grid projects is rising as renewable energy expands and power demand grows.

The 700 billion Korean won contract covers 345 kV cables for a roughly 145 km transmission line, with the supplier's U.S. subsidiary handling delivery. The source does not provide a schedule for when cable deliveries or commissioning will be completed.

The players

LS Cable & System

A South Korean cable manufacturer whose U.S. subsidiary is supplying the cables for the project.

New York Power Authority

A New York state public power entity that is jointly promoting the Propel NY Energy project.

New York Transco

A transmission company jointly promoting the Propel NY Energy project with the New York Power Authority.

The details

LS Cable Systems America, the U.S. subsidiary of LS Cable & System, will supply the cables, along with electrical construction and commissioning tests. The project connects Long Island, Queens, the Bronx and Westchester County and is jointly promoted by the New York Power Authority and New York Transco.

Timeline

  1. February 2026: Contract signed for the Propel NY Energy project.

  2. November 23, 2026: LS Cable & System announced the approximately 700 billion won cable supply.

  3. 2028: LS Marine Solution's ultra-large laying vessel is targeted for deployment.

Roadmap

The Propel NY Energy project is part of a wider effort to bring offshore wind power onto New York's grid by adding high-voltage transmission capacity. This cable contract moves that effort from planning into physical construction.

For New York households and businesses, the project is aimed at stabilizing power supply and expanding capacity as demand grows. The source does not describe any direct effect on electricity rates or service changes for customers.

The takeaway

Large transmission projects like Propel NY Energy depend on specialized suppliers and long construction timelines to bring renewable power to load centers. Tracking contract milestones and commissioning dates will show whether capacity gains arrive on schedule.

Further reading

Explore more utilities coverage for the New York grid projects shaping regional power supply.

Source note: This article includes information reported by 조선일보.

Live Poll

Do you expect your electricity bills to rise as New York expands its power grid?