Pilgrim Hot Springs to Get Geothermal Microgrid

Unaatuq LLC plans a 75-kilowatt geothermal plant and microgrid at the Nome-area site, with construction set for June 2027.

Updated on Nov. 24, 2026 in Utilities

Steam rises from a thermal pool on open tundra, with a single pipe running across gravel toward a small shed under a pale northern sky.
Unaatuq LLC plans a 75-kilowatt geothermal plant and microgrid at Pilgrim Hot Springs near Nome, with construction set for June 2027, backed by a $1.8 million federal grant. AI Illustration. Upload story photo >

Live Poll

Would you support your community investing in local geothermal power to reduce diesel costs?

Unaatuq LLC, a consortium of eight regional organizations, plans to build a 75-kilowatt geothermal power plant and microgrid at Pilgrim Hot Springs near Nome, with construction set to begin in June 2027. The project is funded by federal grants, including a $1.8 million Bureau of Indian Affairs Tribal Climate Resilience Program award made in January 2025.

Why it matters

The microgrid is intended to reduce the site's reliance on diesel, while solar power alone struggles to keep guest cabins supplied, especially during dark fall months. For Alaska, the project adds to a small number of geothermal efforts, as Chena Hot Springs near Fairbanks is the state's only operating geothermal power plant.

The project is backed by a $1.8 million federal grant and a 75-kilowatt geothermal plant drawing water at about 190 degrees Fahrenheit, compared with 165 degrees at Chena Hot Springs. Equipment must travel 53 miles up Kougarok Road plus 7 miles on an access road, and the broader funding timeline remains unresolved.

The players

Unaatuq LLC

A consortium of eight regional organizations that owns the Pilgrim Hot Springs site and is leading the geothermal microgrid project.

Bureau of Indian Affairs

A federal agency within the Department of the Interior that administers the Tribal Climate Resilience Program grant funding the project.

Chena Hot Springs

A resort near Fairbanks that operates Alaska's only geothermal power plant, serving as a comparable reference for the Pilgrim project.

The details

Equipment will be shipped by barge to Nome and then carried over Kougarok Road and an access road to the site, where crews plan to fill the deepest ponds so heavy machinery can pass. The microgrid will supply three rental guest cabins, staff housing, the welcome center, a staff shower room and farm irrigation, replacing solar power that is currently backed up by diesel generators.

Timeline

  1. January 2025: Bureau of Indian Affairs awards the $1.8 million Tribal Climate Resilience Program grant.

  2. June 2026: Geothermal and battery equipment is expected on the first barge to Nome.

  3. August 2026: BIA grant funding is expected to be unfrozen.

  4. Mid- to late May 2027: Kougarok Road is expected to reopen for the season.

  5. June 2027: Geothermal construction is set to begin, with commissioning expected to take most of the following summer.

Market Landscape

Chena Hot Springs near Fairbanks remains Alaska's only operating geothermal power plant, running on water around 165 degrees. The Pilgrim Hot Springs project would extend that model to a remote site near Nome, drawing from cooler water at about 190 degrees and aiming to replace diesel generation in a remote community setting.

Residents and visitors who use the Pilgrim Hot Springs guest cabins and facilities could see a shift from diesel-backed solar to a geothermal-supported microgrid. The project's main effect for users is a more reliable power supply during dark fall months, when the current solar system struggles.

The takeaway

Remote communities relying on diesel power may find geothermal microgrids a practical option where local heat resources exist. The Pilgrim project shows how federal grants and off-site construction can make such systems workable in harsh Alaskan conditions.

What happens next

Equipment is expected on the first barge to Nome in June 2026, Kougarok Road is expected to reopen in mid- to late May 2027, and geothermal construction is set to begin in June 2027.

Further reading

For related context on power generation and grid planning, explore more Utilities coverage on Wisevoter.

Source note: This article includes information reported by Alaska Public Media.