Alaska Approves Loan for Red Dog Mine Solar Farm

A nearly $5 million state loan will help fund an 8.8 MW solar and battery project at the Arctic-adjacent mine to reduce diesel use.

Updated on Nov. 24, 2026 in Science

Alaska Approves Loan for Red Dog Mine Solar Farm

Live Poll

Do you support state loans to help fund energy projects like this one?

The Alaska Energy Authority board unanimously approved a nearly $5 million loan from the Power Project Fund for a solar farm at Red Dog Mine. Tugliq Red Dog will build, own and operate the roughly $35 million project, which will sell electricity to mine operator Teck Alaska.

Why it matters

The Red Dog Mine currently burns about 40,000 gallons of diesel a day, and the project is intended to add a second power source during peak summer demand. It reflects a broader push across Alaska's remote operations to reduce dependence on diesel generation.

The Power Project Fund loan covers roughly $5 million of a $35 million project, with the remainder not described in the source. The project's expected 5% share of current mine electricity compares with the 90% annual coverage projected after mining ends, and the expansion scenario's 3% figure remains unexplained.

The players

Alaska Energy Authority

The state agency that approved the loan from its Power Project Fund to finance energy infrastructure across Alaska's remote communities and industrial sites.

Teck Alaska

The operator of the Red Dog zinc and lead mine in northwest Alaska, which will purchase the solar project's electricity.

Tugliq Red Dog

The entity that will build, own and operate the solar and battery project at the Red Dog Mine site.

The details

Tugliq Red Dog's 8.8 MW system with 15 MWh of storage will use more than 15,000 panels across about 30 acres at the mine, roughly 105 miles north of the Arctic Circle. The mine's land is owned by NANA, an Iñupiat-owned Alaska Native corporation, and site work began in June.

Timeline

  1. June: Site work on the solar project began.

  2. October 2028: The solar and storage project is expected to come online.

  3. 2031: Existing deposits are expected to support mine operations through this year.

Roadmap

The Red Dog project extends Alaska's solar-plus-storage approach, previously used in remote village microgrids, to a large industrial mining operation. Its 90% post-mining coverage projection shows how such systems can be designed to outlast the mine's operating life.

For Alaskans, the project signals a possible long-term reduction in the diesel that powers remote industry, which could affect fuel-dependent costs across the state's energy economy. The arrangement also shows how a mine's power purchases can be structured around a third-party operator.

The takeaway

Remote industrial operations in Alaska are testing whether solar and battery storage can supplement or eventually replace diesel generation. Projects like this one show that the economics depend on loans, power purchase agreements and long operating horizons.

What happens next

The solar and storage project is expected to come online in October 2028, a date the source projects but which will confirm whether construction stays on schedule.

Further reading

Explore more on Alaska energy developments and how remote projects are changing power supply.

Source note: This article includes information reported by Electrek.