King Cove Appeals Ruling Blocking Cold Bay Road
The 19-mile road through the Izembek National Wildlife Refuge is on hold after a federal court invalidated a 2025 land exchange.
Updated on Nov. 24, 2026 in Industry

Live Poll
Should a road through a wildlife refuge be built to speed emergency medical access?
King Cove Corporation has filed an appeal with the U.S. Ninth Circuit Court to reverse an August federal court order that blocks construction of a 19-mile road from King Cove to Cold Bay. The ruling invalidated a 2025 land exchange between the federal government and the corporation.
Why it matters
The road would cross the Izembek National Wildlife Refuge and connect King Cove to Cold Bay's all-weather airport. Residents say it could save lives by allowing people to reach the airport during medical emergencies when weather grounds flights out of King Cove.
The proposed road spans 19 miles, and construction has completed about 2 miles of it, with the first nearly 3 miles on land the corporation already owns. Whether the Ninth Circuit will reverse the August order that blocks further work remains unresolved.
The players
King Cove Corporation
A Native corporation representing the Alaska Native community of King Cove, which pursued the land exchange and the road to improve access to medical care.
The details
A federal court order issued in August invalidated a 2025 land exchange that would have given King Cove Corporation ownership of land within the wildlife refuge, a step needed to build the road through it. Construction on the first road section began in September, and the first two miles are complete, with work scheduled to resume in the spring.
Timeline
August 2026: Federal court order invalidated the 2025 land exchange and blocked construction.
September 2026: Construction began on the first road section.
November 2026: King Cove Corporation filed its appeal with the Ninth Circuit.
Spring 2027: The court is expected to take up the appeal and construction is scheduled to resume.
Market Landscape
The dispute sits within a long-running conflict over road access through Izembek, shaped by refuge protections set under the Alaska National Interest Lands Conservation Act. The August ruling and the pending appeal extend that conflict into a new round of litigation over the 2025 land exchange.
The outcome of the appeal determines whether residents of King Cove gain a reliable land route to Cold Bay's all-weather airport during medical emergencies. Until the court rules, the road remains partially built and stalled.
The takeaway
The case shows how land exchanges within federal wildlife refuges can determine whether remote communities gain practical access to emergency services. Its resolution will hinge on the Ninth Circuit's review of the 2025 exchange.
What happens next
The Ninth Circuit is expected to take up King Cove Corporation's appeal next spring, and construction could resume if the court rules by April or May.
Further reading
For related coverage, explore more Construction news from across Alaska.