Chevron Gets Approval for Geryon and Eurytion Drilling
Regulator NOPSEMA has accepted Chevron Australia's environment plan for six new subsea gas production wells in the Northern Carnarvon Basin.
Updated on Nov. 29, 2026 in Oil and Gas

The National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA) accepted Chevron Australia's environment plan for drilling at the Geryon and Eurytion gas fields, which cover six new subsea production wells clustered around a single drilling centre. The fields are the first of seven backfill fields Chevron plans to develop to supply the Gorgon gas development.
Why it matters
The approval clears a regulatory step for the Gorgon backfill programme, which is intended to sustain gas supply from the project. Drilling is scheduled to begin in early 2027, subject to rig, vessel and equipment availability, approvals and weather.
The plan covers six subsea production wells with drilling and completions estimated at 12 to 18 months across one or more campaigns, in water about 1,221 m deep. Timing for the remaining five backfill fields in the Western Australia gas programme has not been disclosed.
The players
Chevron Australia
The Australian arm of the US energy major Chevron, which operates the Gorgon gas project off Western Australia.
NOPSEMA
The National Offshore Petroleum Safety and Environmental Management Authority, the federal regulator that assesses and accepts offshore petroleum environment plans.
The details
The wells lie in retention lease WA-22-R, and Chevron awarded the major subsea contract for Gorgon Stage 3 to TechnipFMC in December 2025, with Subsea7 winning the installation work. The other backfill fields are Chandon, Chrysaor, Dionysus, Semele and West Tryal Rocks.
Timeline
December 2025: TechnipFMC awarded the Gorgon Stage 3 subsea contract and Subsea7 won installation work.
27 November 2026: NOPSEMA accepted Chevron Australia's environment plan.
Early 2027: Drilling and completions are scheduled to start.
Market Landscape
The Geryon and Eurytion approval is the first of seven backfill fields Chevron plans for the Gorgon gas development in the Northern Carnarvon Basin. It shows the operator extending the life of existing Western Australian gas supply through subsea tiebacks rather than new standalone projects.
For Western Australian households and businesses, the approval supports continued gas supply from the Gorgon development through the backfill programme. The drilling programme itself does not change prices or availability in the near term.
The takeaway
Long-running gas projects often depend on a series of smaller regulatory approvals, and each step, such as this environment plan, signals whether planned production is progressing on schedule.
What happens next
Drilling and completions at the Geryon and Eurytion fields are scheduled to start in early 2027, with timing subject to rig, vessel and approval availability.
Further reading
Explore more on Oil and Gas activity across Western Australia's offshore basins.
Source note: This article includes information reported by World Oil.