Nexans Completes Chevron Jansz-Io Subsea Cable
Nexans has finished laying and trenching a high-voltage dynamic cable for Chevron's offshore Jansz-Io Compression project in Western Australia.
Updated on Nov. 20, 2026 in Industry

Cable-laying vessel Nexans Aurora completed installation and trenching of a 145 kV dynamic cable for Chevron's Jansz-Io Compression project offshore Western Australia. The cable runs from Barrow Island to a floating field control station and powers seabed compressors.
Why it matters
The Jansz-Io Compression project uses subsea compression to sustain gas supply to the Gorgon LNG and domestic gas plants on Barrow Island. Completing the power link is a step toward keeping that gas flowing to Western Australian facilities.
The installation included 26 buoyancy modules and 30 kilometres of trenched cable along a route of about 135 kilometres rated at 145 kV. Rock stabilisation along the final 28 kilometres and cable jointing remain before handover.
The players
Chevron
Chevron is a major American multinational energy company with large liquefied natural gas operations in Australia, including the Gorgon project on Barrow Island.
Nexans
Nexans is a French cable and cabling systems manufacturer that supplies high-voltage subsea power cables for offshore energy projects.
The details
The cable head was overboarded and pulled in to the field control station, and buoyancy modules were installed using a horizontal method. The operation also included about 200 metres of vortex-induced vibration strakes in the Scarp section.
Timeline
23 October: Nexans Aurora left Australia after completing the cable work.
February: A final soak test is planned before handover.
Context
The Jansz-Io Compression project extends the existing Gorgon LNG operation on Barrow Island by adding subsea compression that keeps gas flowing to the plant. The cable is the power link that drives those seabed compressors from the island.
For Western Australian households and businesses, the project is designed to sustain domestic gas supply from the Barrow Island plants. Completion of the power link helps keep that supply secure ahead of handover.
The takeaway
Reliable subsea power is what keeps remote offshore gas compression running, so cable completion is a key milestone for supply continuity. Watching the planned February soak test will show whether the system is ready for handover.
What happens next
Cable jointing at the field control station and on Barrow Island, rock stabilisation along the final 28 kilometres, and a final soak test planned for February remain before handover.