Chevron Vented Methane From Gorgon Facility

Western Australia's environmental regulator has confirmed Chevron deliberately released methane from its Barrow Island LNG plant, prompting calls for stronger oversight.

Updated on Nov. 25, 2026 in Industry

Bold flat-color editorial illustration of a single slender vent stack on a low arid coastline, with a thin pale plume drifting over a calm sea.
Western Australia's environmental regulator confirmed Chevron deliberately vented methane from its Gorgon LNG plant on Barrow Island, prompting calls for stronger oversight. AI Illustration. Upload story photo >

Live Poll

Do you trust big companies to police their own pollution?

Western Australia's environmental regulator confirmed Chevron deliberately vented methane from the Gorgon LNG facility on Barrow Island. Satellite data captured plumes from the site in five consecutive passes from November 2025, including a 7.8 tonne-per-hour release in August.

Why it matters

The venting comes from a shortfall in the Gorgon carbon capture and storage system, which has not met its requirement to inject at least 80 per cent of reservoir carbon dioxide back underground. The incident raises questions for Western Australian regulators about monitoring and the reliance on carbon offsets.

Satellite data from Carbon Mapper's Tanager-1 recorded the August plume at 7.8 tonnes per hour, well above the EPA super emitter threshold of 100 kilograms per hour. Chevron has used carbon offsets elsewhere to cover the shortfall against its requirement to reinject 80 per cent of reservoir carbon dioxide.

The players

Chevron

Chevron is a major American multinational energy company that operates the Gorgon LNG project on Barrow Island in Western Australia.

Matthew Swinbourne

Matthew Swinbourne is the Western Australian Environment Minister who wrote to the Environmental Protection Authority seeking additional monitoring and reporting conditions on Chevron.

The details

Chevron told state investigators during a visit on 5 and 6 November that the release was deliberate venting of reservoir carbon dioxide from the facility's acid gas removal units. The United Nations Environmental Programme reported the August plume to the Department of Water and Environmental Protection, and the department's investigation was finalised the week before a Wednesday upper house hearing.

Timeline

  1. November 2025: Satellite begins capturing methane plumes from the Gorgon facility.

  2. August: The largest 7.8 tonne-per-hour plume is recorded.

  3. 5 and 6 November: Chevron tells investigators the release was deliberate venting.

  4. Wednesday: Upper house committee hearing, where the minister confirms the venting was deliberate.

Legacy Obligations

The Gorgon project's carbon capture approval required Chevron to reinject at least 80 per cent of reservoir carbon dioxide underground, and the current venting shows that obligation has not been met. Chevron has used carbon offsets elsewhere to make up the gap, a practice that now faces scrutiny from state regulators.

Residents and workers in Western Australia's resources sector may face tighter environmental oversight if the state's regulator adds monitoring and reporting conditions to Chevron's operations. The outcome could affect how future gas projects in the state are approved and monitored.

The takeaway

The Gorgon case shows that carbon capture obligations depend on enforcement and monitoring as well as approval conditions. Readers following the state's resource sector should watch whether the Environmental Protection Authority adopts the minister's proposed conditions.

Further reading

Explore more on Oil and Gas developments affecting Western Australia's resource sector.

Source note: This article includes information reported by Brisbane Times.

Live Poll

Do you trust big companies to police their own pollution?