Maritana Advances Black Swan Processing Hub Build

Construction at Maritana Minerals' Black Swan processing hub in Western Australia is progressing ahead of schedule, with first gold targeted for 2027.

Updated on Nov. 27, 2026 in Industry — General

Economist-style flat-color editorial illustration of cylindrical tanks beside a low processing building on red earthworks under a pale sky, representing a goldfields processing hub.
Maritana Minerals says construction of its Black Swan processing hub near Kalgoorlie is ahead of schedule, with first gold targeted for the second half of 2027. AI Illustration. Upload story photo >

Maritana Minerals is advancing construction of its Black Swan processing hub, approximately 50km north-east of Kalgoorlie, with carbon-in-leach tank foundations ahead of schedule. The company remains on track to deliver first gold from the facility in the second half of 2027.

Why it matters

The redevelopment will establish an annual ore processing capacity of 2.5 million tonnes, a substantial addition to regional processing capacity in Western Australia's goldfields. Progress on the hub signals the project is moving toward production under an extended early works agreement with GR Engineering Services.

The redevelopment will establish an annual ore processing capacity of 2.5 million tonnes at the Black Swan hub, located about 50km north-east of Kalgoorlie. Four carbon-in-leach tank foundations are available for steelwork installation, but the principal EPC contract remains under finalisation.

The players

Maritana Minerals

Maritana Minerals is the company developing the Black Swan processing hub in Western Australia's goldfields.

GR Engineering Services

GR Engineering Services is the contractor carrying out construction works at the Black Swan site under an extended early works agreement.

The details

Construction of the carbon-in-leach tank foundations is ahead of schedule, and the SAG mill liner removal is complete. Refurbishment of the crushing circuit is underway, fabrication of the pre-leach thickener is complete, and bulk earthworks for the expanded run-of-mine pad are nearing completion. Off-site refurbishment of the primary jaw crusher and SAG mill is being prepared, and the expanded pad will accommodate ore from multiple regional mining operations, with material stockpiled and blended before processing.

Timeline

  1. End of November 2026: installation of the carbon-in-leach tanks is set to commence.

  2. Second half of 2027: first gold is expected from the Black Swan processing hub.

Industry Context

The Black Swan hub extends the Kalgoorlie goldfields' role as a shared processing centre, adding 2.5 million tonnes of annual capacity that can take ore from several regional mines. Its design to blend and stockpile third-party material places it within the goldfields' established model of centralised processing.

For residents of the goldfields region, the hub's expansion is expected to bring additional processing activity and construction employment to the area. The project's progress toward first gold in 2027 means the regional processing landscape will change within the next two years.

The takeaway

Watch the Black Swan project's progress against its end-2026 tank installation and 2027 first-gold targets, as these milestones will show whether the redevelopment stays on schedule.

What happens next

Installation of the carbon-in-leach tanks is set to commence by the end of November 2026, with first gold expected in the second half of 2027.

Further reading

For more on the wider sector, see Industry — General coverage across Western Australia.

Source note: This article includes information reported by Australian Mining.