Forrestania Delivers First Ore at Edna May

Forrestania Resources has begun wet commissioning at its Edna May gold mine in Western Australia, with first gold planned for December 2026.

Updated on Nov. 23, 2026 in Business

Forrestania Delivers First Ore at Edna May

Forrestania Resources delivered first ore into the primary crusher at its Edna May gold mine, about 11 weeks after taking operational control of the site on 4 September. The company is testing and optimising processing circuits as part of a staged commissioning program.

Why it matters

The milestone moves the Edna May project closer to production, with combined run-of-mine stockpiles across Edna May and Lake Johnston exceeding 250,000 tonnes. Western Australia's gold sector gains another project ramping towards its planned first gold pour.

Forrestania's combined run-of-mine stockpiles across Edna May and Lake Johnston have exceeded 250,000 tonnes, ahead of commissioning. The company's mineral resource inventory has grown from approximately 300,000 ounces to more than three million ounces over the past year.

The players

Forrestania Resources

An Australian mining company that has expanded its mineral resource inventory and taken control of the Edna May gold mine in Western Australia.

Australian Gold Reagents

A supplier of gold processing reagents that has entered a long-term sodium cyanide supply agreement with Forrestania Resources.

Campbell Gold Haulage

A mining logistics contractor engaged by Forrestania Resources for ore loading and crusher feed at Edna May.

The details

Forrestania Resources began wet commissioning at Edna May after the arrival of semi-autogenous grinding mill liners on site. The company also secured a long-term sodium cyanide supply agreement with Australian Gold Reagents and an ore-loading and crusher-feed contract with Campbell Gold Haulage.

Timeline

  1. 4 September: Forrestania formally took operational control of Edna May.

  2. 20 November: Forrestania announced key supply and mining services agreements.

  3. December 2026: First gold pour is planned at Edna May.

Market Landscape

Forrestania's move from a resource base of roughly 300,000 ounces to more than three million ounces positions it among Western Australia's gold developers seeking to convert resources into production. Securing cyanide supply and haulage contracts before first pour reflects the supply-chain groundwork such projects require.

For shareholders, the commissioning milestone is an operational step rather than revenue, and the December 2026 gold pour remains a planned date. Investors will be watching whether commissioning stays on schedule and whether the expanded resource base converts into production.

The takeaway

Progress at Edna May shows how a resource-stage company moves towards production through staged commissioning and supply contracts. Readers tracking Western Australian gold should watch for confirmation of the December 2026 first pour.

What happens next

Forrestania Resources plans its first gold pour at Edna May in December 2026, following continued commissioning across the plant's processing circuits.