NRW Holdings Named Bullabulling Gold Mining Contractor
NRW Holdings has been selected as preferred mining contractor for Minerals 260's Bullabulling gold project in Western Australia, with early works starting immediately.
Updated on Nov. 26, 2026 in Corporate Finance

NRW Holdings was selected as preferred mining contractor for the Bullabulling gold project, owned by Minerals 260 Limited's subsidiary Bullabulling Operations Pty Ltd. Early mining services activities will commence immediately ahead of full mobilisation to site in the September quarter of 2027.
Why it matters
The contract offers NRW a five-year mining services agreement with an option to extend, valued at an anticipated circa-A$1 billion over the first five years. It also gives Minerals 260 a contractor in place ahead of its planned 2028 first production target.
The anticipated value of the first five years of mining services is circa-A$1 billion ($664 million), with circa-A$20 million of new capital deployed in FY28 and circa-A$80 million from year three. The long-form contract remains subject to Minerals 260's Final Investment Decision expected in early 2027.
The players
NRW Holdings
NRW Holdings is an Australian mining services contractor whose subsidiary Action Drill & Blast Pty Ltd handles drill and blast work.
Minerals 260 Limited
Minerals 260 Limited is an Australian mining company developing the Bullabulling gold project in Western Australia.
The details
The scope covers mine site establishment, pre-stripping, dewatering, load and haul, drill and blast, and ancillary services, with the drill and blast work undertaken by NRW subsidiary Action Drill & Blast Pty Ltd. The mining fleet will be substantially provided from NRW's existing idle fleet, with staged development and ramp-up over the first three years of the contract.
Timeline
Early 2027: expected execution of the long-form contract at Final Investment Decision.
September quarter of 2027: full mobilisation to site planned.
December quarter of 2027: mining expected to start.
2028: Minerals 260's first production target.
Corporate Finance Pattern
Appointing a contractor before a Final Investment Decision, with the fleet drawn from idle equipment, lowers the capital needed up front for Western Australian gold developers. Minerals 260 has tied its 2028 production timetable to this contractor arrangement.
For Western Australian residents, the project signals future mining employment and contracting activity as early works and full mobilisation proceed through 2027. The timeline is tied to a Final Investment Decision not yet made, so start dates may shift.
The takeaway
A contractor appointment ahead of final investment approval can accelerate a project's timeline, but readers should note the long-form contract is not yet signed.
What happens next
The long-form contract is expected to be executed at Minerals 260's Final Investment Decision in early 2027, with full mobilisation to site planned for the September quarter of 2027.