Downer Wins $1.1 Billion NSW Transmission Contract

Downer EDI will build 110 kilometres of 500kV line for the Hunter Transmission Project under a three-year deal with Energy Corporation NSW.

Updated on Nov. 23, 2026 in Industry

Photograph of a row of lattice steel transmission towers crossing rolling eucalypt-covered hills under golden-hour light, illustrating new high-voltage grid construction in New South Wales.
Downer EDI has won a three-year, $1.1 billion contract with Energy Corporation NSW to build 110 kilometres of 500kV transmission line for the Hunter Transmission Project. AI Illustration. Upload story photo >

Downer EDI has secured a three-year, $1.1 billion contract with Energy Corporation NSW to deliver approximately 110 kilometres of double circuit 500kV transmission line. The work runs from the Bayswater South switching station to the Olney switching station and will be carried out with Transgrid.

Why it matters

The Hunter Transmission Project is part of the state's electricity infrastructure roadmap to expand large-scale renewable energy and supports the retirement of end-of-life coal-fired power stations. The contract signals a major phase of grid construction across New South Wales.

The $1.1 billion, three-year contract covers roughly 110 kilometres of 500kV double circuit line with lattice steel structures. The source does not state how costs are allocated across the works or what the project's total budget is.

The players

Downer EDI

Downer EDI is an Australian engineering and infrastructure services company active in utilities and transmission projects.

Energy Corporation NSW

Energy Corporation NSW is the New South Wales state-owned energy entity commissioning the Hunter Transmission Project.

Transgrid

Transgrid is the New South Wales electricity transmission network operator working on the project's transmission line works.

The details

Downer EDI will deliver the new line and lattice steel structures and will work alongside Transgrid on the transmission line works. The Hunter Transmission Project line runs between the Bayswater South and Olney switching stations in NSW.

Timeline

  1. December: Hunter Transmission Project works are set to commence.

  2. 2027: On-site mobilisation for the project is to occur.

Roadmap

The Hunter Transmission Project forms part of New South Wales' electricity infrastructure roadmap to increase large-scale renewable energy. The contract advances that roadmap from planning into physical construction.

For households and businesses in New South Wales, the project is part of the infrastructure that will carry electricity from new generation sources across the grid. The source does not specify any direct change to consumer tariffs or service.

The takeaway

The contract marks a concrete step in the Hunter Transmission Project, shifting New South Wales' grid plans toward construction. Watch for the December start and 2027 mobilisation as the next visible milestones.

What happens next

Works on the Hunter Transmission Project are set to commence in December, with on-site mobilisation to follow in 2027.