EDF Acquires Holloway Battery Storage Project

The 250 MW, 1 GWh project in the New England Renewable Energy Zone is currently under development in New South Wales.

Updated on Nov. 19, 2026 in Energy

Grey steel battery storage containers and a utility substation with lattice towers stand on dry golden grassland under a wide open sky.
EDF power solutions Australia has acquired the 250 MW Holloway battery storage project in New South Wales from SynCo Global, a four-hour facility in the New England Renewable Energy Zone. AI Illustration. Upload story photo >

Live Poll

Do you trust Australia's electricity grid to stay reliable as renewables expand?

EDF power solutions Australia has acquired the Holloway Battery Energy Storage System project from SynCo Global. The 250 MW battery provides four hours of storage and is located in the New England Renewable Energy Zone.

Why it matters

The battery stores excess renewable energy when supply is high and discharges it during peak demand, helping balance the grid across New South Wales. The acquisition expands EDF power solutions Australia's portfolio of renewable energy and storage projects.

The project's specifications are 250 MW of power and 1 GWh of energy, providing four hours of storage. Its Environmental Impact Statement is expected on public exhibition in coming months, and the investment decision remains pending.

The players

EDF power solutions Australia

The Australian arm of the French energy company EDF, active in renewable generation and battery storage projects.

SynCo Global

The company that developed the Holloway battery project before selling it to EDF power solutions Australia.

The details

The Holloway battery is close to key grid infrastructure in the New England Renewable Energy Zone, which includes solar and wind production assets. The project is currently under development and is being acquired by EDF power solutions Australia from SynCo Global.

Timeline

  1. Coming months: Environmental Impact Statement expected on public exhibition

  2. Late 2027: Final Investment Decision targeted

  3. 2029: Holloway battery operations to commence

Energy Transition

The Holloway project follows the pattern of grid-scale batteries being built alongside wind and solar in New South Wales to firm variable renewable output. It adds to the storage capacity needed as coal generators retire across the National Electricity Market.

Storage projects like Holloway help keep electricity supply steady when solar and wind output drops, which can support more reliable power for households and businesses across New South Wales. The project's timeline means these benefits will not arrive until operations begin around 2029.

The takeaway

Grid-scale batteries are increasingly the bridge between renewable generation and reliable supply. Watching for the Environmental Impact Statement will show how the Holloway project's local effects are assessed before construction proceeds.

What happens next

The Holloway battery's Environmental Impact Statement is expected to go on public exhibition in coming months, followed by a Final Investment Decision targeted for late 2027 and operations scheduled to commence in 2029.

Further reading

Explore more energy storage coverage to see how batteries are reshaping New South Wales's grid.

Source note: This article includes information reported by Renewable Energy Magazine, at the heart of clean energy journalism.

Live Poll

Do you trust Australia's electricity grid to stay reliable as renewables expand?