Acciona Builds 100th Tower for Central-West Orana Zone
The 70-metre transmission tower is part of the first renewable energy zone formed in Australia, with power delivery expected from 2028.
Updated on Nov. 20, 2026 in Energy

Live Poll
Do you think your area's electricity supply is getting more reliable?
Acciona has erected the 100th transmission tower for the Central-West Orana Renewable Energy Zone in New South Wales. The 70-metre, 48-tonne double-circuit steel lattice tower will support two independent 500 kV electrical circuits.
Why it matters
The project is expected to start delivering clean, reliable energy to New South Wales from 2028. HumeLink East and West are expected to strengthen the state grid and unlock new capacity, including from Snowy 2.0.
The 100th tower measures 70 metres and weighs 48 tonnes, carrying two 500 kV circuits across a corridor that includes 90 kilometres of 500 kV and 150 kilometres of 330 kV lines. HumeLink East has 157 towers installed along 225 kilometres of 500 kV overhead line, with the 200th tower expected in the coming weeks.
The players
Acciona
Acciona is a Spanish multinational infrastructure and renewable energy company that leads construction on both projects and is a partner in ACEREZ.
Transgrid
Transgrid is the New South Wales electricity transmission network operator responsible for delivering the HumeLink East project.
Endeavour Energy
Endeavour Energy is an electricity distribution network operator in New South Wales and a partner in the ACEREZ consortium developing the Central-West Orana zone.
The details
Stringing of conductors between completed towers is underway using helicopters. Civil works on the Bannaby 500 kV substation expansion are nearing completion, while the joint venture of Acciona and Genus delivers HumeLink East for Transgrid between Bannaby and Wondalga.
Timeline
Coming weeks: the 200th HumeLink East transmission tower is expected to be built.
2028: the Central-West Orana Renewable Energy Zone is expected to begin delivering energy to the state.
Past 12 months: Acciona and Genus have passed the one-year construction mark on HumeLink East.
The Tech Race
The Central-West Orana zone was the first renewable energy zone formed in Australia, and this milestone marks progress from designation toward the transmission build-out needed to deliver its power. The 500 kV HumeLink East line is part of a wider effort to connect new generation capacity to the New South Wales grid.
New South Wales households and businesses will eventually draw on power from the Central-West Orana zone once it begins delivering energy from 2028. The stronger grid and added capacity from HumeLink East and West are intended to support reliable supply across the state.
The takeaway
Large transmission builds are measured in towers and kilometres, and each completed milestone brings the state closer to delivering new renewable capacity to its grid. Readers following the energy transition can track the 2028 start date as the key marker for when the zone begins supplying power.
What happens next
The 200th HumeLink East transmission tower is expected to be built in the coming weeks, and the Central-West Orana zone is expected to begin delivering energy from 2028.
Further reading
For more on the state's power projects, explore the Energy section covering New South Wales.
Source note: This article includes information reported by RenewEconomy.