EnEarth Launches CO₂ Storage Market Test at Prinos
The Market Test opens access to CO₂ storage capacity at Greece's Prinos project through a staged, non-binding and then binding process.
Updated on Nov. 24, 2026 in Oil and Gas

EnEarth has launched the Market Test for the CO₂ storage facility at Prinos in northern Greece, following the project's February 2026 CO₂ storage permit. The process begins with a Non-Binding Stage on 24 November 2026 and will move to a Binding Stage afterward.
Why it matters
The launch follows significant progress in developing Prinos, which is described as one of Europe's most advanced CO₂ storage projects. The framework sets out how interested parties can request storage capacity on an open, transparent and non-discriminatory basis.
The Market Test runs from a Non-Binding Stage starting 24 November 2026 to binding Access Contracts targeted for the third quarter of 2027. Capacity volumes, pricing and the number of applicants have not been disclosed.
The players
EnEarth
EnEarth is the company operating the Prinos CO₂ storage project and running its Market Test for storage capacity.
The details
Under the Market Test, interested parties first submit non-binding expressions of interest, then move to binding capacity requests, capacity allocation and long-term commercial agreements. Successful applicants in the Non-Binding Stage will be invited to enter Joint Development Agreements with EnEarth.
Timeline
February 2026: Prinos granted a CO₂ storage permit.
24 November 2026: Non-Binding Stage of the Market Test begins.
Mid-January 2027: Joint Development Agreements are aimed to be signed.
First quarter of 2027: Cooperation under the agreements is expected to continue.
Third quarter of 2027: EnEarth aims to conclude binding Access Contracts.
Industry Shift
The Prinos Market Test moves geological CO₂ storage beyond single-operator projects toward open, third-party access to storage capacity. This structure follows the commercial model of carbon storage developments that seek to serve multiple emitters in the region.
Companies seeking CO₂ storage capacity can prepare by responding to the Non-Binding Stage starting 24 November 2026. Successful applicants would then enter Joint Development Agreements before binding capacity commitments are made.
The takeaway
Access to CO₂ storage is being structured as an open, staged process rather than a closed arrangement, which may shape how emitters plan carbon capture commitments. Interested parties should track the November 2026 start date and the subsequent agreement milestones.
What happens next
Joint Development Agreements are targeted for signing in mid-January 2027, and the Binding Stage is scheduled to follow, subject to approvals.
Further reading
Explore more on Oil and Gas developments shaping energy infrastructure worldwide.
Source note: This article includes information reported by Η Ναυτεμπορική.