Samsung Names Petronas' PFLNG TIGA Floating LNG Unit
The naming ceremony at Samsung Heavy Industries' Geoje Shipyard marks a milestone for Petronas' third floating LNG facility.
Updated on Nov. 25, 2026 in Oil and Gas

Samsung Heavy Industries held a naming ceremony for PFLNG TIGA at its Geoje Shipyard in South Korea on November 24. The facility is Petronas' third floating LNG facility and Malaysia's first nearshore FLNG facility.
Why it matters
PFLNG TIGA adds 2.0 million tons per annum of LNG production capacity to Petronas' portfolio once operational. The project reflects the continued role of JGC Corporation and Samsung Heavy Industries in large-scale LNG infrastructure.
PFLNG TIGA is rated at 2.0 million tons per annum of LNG production capacity, a figure the source does not compare with other Petronas facilities. The source does not detail how the unit's output will be commissioned ahead of its scheduled 2027 start.
The players
Petronas
Petronas is Malaysia's national oil and gas company, operating LNG production facilities including the PFLNG TIGA unit.
JGC Corporation
JGC Corporation is a Japanese engineering and construction firm that has supported Petronas' LNG business for five decades and completed EPC work for all nine LNG production trains at the Bintulu LNG Complex.
Samsung Heavy Industries
Samsung Heavy Industries is a South Korean shipbuilder and offshore engineering company responsible for the FLNG hull EPC work and modular topside fabrication for PFLNG TIGA.
The details
The naming ceremony was held at Samsung Heavy Industries' Geoje Shipyard, with Datin Azmah Azman serving as Lady Sponsor. The engineering, procurement, construction, and commissioning work is led by a JGC Corporation consortium that includes Samsung Heavy Industries, which handles the FLNG hull EPC work and modular topside fabrication.
Timeline
November 24, 2026: Naming ceremony held for PFLNG TIGA at the Geoje Shipyard.
February 2027: Planned sail-away from the Geoje Shipyard.
2027: Scheduled start of LNG production.
Roadmap
PFLNG TIGA extends the pattern set by JGC Corporation's completion of EPC work for all nine LNG production trains at the Bintulu LNG Complex, moving the same engineering partnership from onshore trains to a floating unit. The project continues Petronas' expansion of floating LNG capacity, with TIGA as its third floating facility.
The facility's 2.0 million tons per annum capacity will feed into Petronas' LNG supply once production starts in 2027. The source does not indicate any direct change to pricing or availability for end consumers.
The takeaway
Large LNG projects typically move through naming, sail-away and commissioning in stages, so the February 2027 sail-away is the next checkpoint to watch before production begins that year.
What happens next
PFLNG TIGA is planned to sail away from the Geoje Shipyard in February 2027, with LNG production scheduled to start in 2027.
Further reading
For broader context on the industry, see the Oil and Gas section.
Source note: This article includes information reported by Offshore-energy.