AIS Supplies Cable Protection for South Korean Wind Farm
The contract covers 55 NjordGuard systems and 54 bellmouths for the 390MW Shinan-Ui offshore wind project.
Updated on Nov. 23, 2026 in Energy

AIS has secured a contract with LS Marine Solution to supply cable protection systems and bellmouths for the Shinan-Ui offshore wind farm in South Korea. The order covers 55 NjordGuard cable protection systems and 54 associated bellmouths.
Why it matters
The NjordGuard systems protect submarine cables against environmental forces, abrasion, over-bending and other dynamic effects, which is central to keeping power flowing from offshore turbines to shore. The contract also has AIS manufacturing bellmouths at its facility in the North West of England, tying the project to UK production.
The Shinan-Ui farm is rated at 390MW with 26 turbines of 15MW each, connected by 66kV inter-array cables and two 154kV export cables. The contract value and the full delivery timetable were not disclosed in the source.
The players
AIS
AIS is a supplier of cable protection and subsea equipment that manufactures bellmouths at its facility in the North West of England.
LS Marine Solution
LS Marine Solution is the South Korean counterparty that contracted AIS to supply the cable protection systems and bellmouths for the project.
The details
AIS will supply NjordGuard cable protection systems that incorporate API 17L-certified Uraduct material to improve seabed wear resistance, alongside bellmouths for the project. Engineering work is scheduled to begin immediately, with delivery to South Korea expected to be completed in August 2027.
Timeline
Engineering work on the cable protection systems begins immediately.
Delivery to South Korea is expected to be completed in August 2027.
Roadmap
The order extends the NjordGuard system, which uses API 17L-certified Uraduct material for seabed wear resistance, into a 390MW South Korean offshore wind build. It reflects the continued expansion of offshore wind capacity in East Asia and the demand for protective hardware on export and inter-array cabling.
The cable protection and bellmouth hardware being supplied is intended to keep offshore wind export and inter-array cables protected over a 28-year design life. For the public, this translates into more protected grid infrastructure feeding electricity from the Shinan-Ui farm to shore.
The takeaway
Offshore wind projects depend on less visible components such as cable protection systems, whose durability over decades shapes whether the turbines deliver reliable power. Watching supplier contracts like this one shows where the supply chain for large-scale renewable builds is expanding.
Further reading
For more on how wind and other power sources are reshaping grids, explore our Energy coverage.
Source note: This article includes information reported by Renews.