Fengmiao 1 Offshore Substation Energised in Taiwan

Copenhagen Offshore Partners brings the transmission system of the 495 MW Fengmiao 1 offshore wind farm fully online.

Updated on Nov. 13, 2026 in Oil and Gas

Bold flat-color editorial illustration of a lone offshore substation platform on steel legs above calm navy sea, with pale horizon.
Copenhagen Offshore Partners energised the offshore substation at Taiwan's 495 MW Fengmiao 1 wind farm in October, with grid connection scheduled for late 2027. AI Illustration. Upload story photo >

Copenhagen Offshore Partners energised the offshore substation at the 495 MW Fengmiao 1 offshore wind farm in Taiwan in October 2026. Energisation brings the project's transmission system fully online while turbine foundation installation continues.

Why it matters

The milestone moves the project toward grid connection, which is scheduled for the end of 2027. It marks progress on Taiwan's offshore wind build-out as the wider energy transition continues.

The offshore substation topside weighs 3,400 tonnes and its jacket weighs 8,000 tonnes, with the 495 MW project to be built from 33 Vestas V236-15.0 MW turbines. Turbine foundation work is still underway, and the remaining installation schedule has not been detailed.

The players

Copenhagen Offshore Partners

Copenhagen Offshore Partners is an offshore wind developer and a part of the Copenhagen Infrastructure Partners investment group that is developing the Fengmiao 1 project.

CSBC-DEME Wind Engineering

CSBC-DEME Wind Engineering is a joint venture between Belgian marine contractor DEME and Taiwanese shipbuilder CSBC that handles offshore wind installation work.

The details

CSBC-DEME Wind Engineering installed the offshore substation foundation and topside in August 2026 using the heavy-lift vessel Green Jade. Jan De Nul then pulled the two export cables into the substation, while Semco Maritime and PTSC Mechanical & Construction built the substation structures. Pin piles for the three-legged turbine jacket foundations were installed in summer 2026.

Timeline

  1. Summer 2026: Pin piles installed for the turbine jacket foundations.

  2. August 2026: Offshore substation foundation and topside installation completed.

  3. October 2026: Offshore substation energised.

  4. End of 2027: Scheduled grid connection for Fengmiao 1.

Industry Trajectory

Fengmiao 1 is one of the large offshore wind projects within Taiwan's offshore wind development program. Its energisation shows the program moving from foundation and substation work toward operational grid connection.

Grid connection by the end of 2027 would add 495 MW of offshore wind capacity to Taiwan's power supply once the project is complete. For consumers, the project's progress points to the power sources that could feed the grid in the coming years.

The takeaway

Large offshore wind projects advance in stages, from foundations and substations to cable connection and grid energisation. Tracking each milestone shows how close a project is to delivering power.

What happens next

Turbine foundation installation will continue as weather windows allow, with grid connection scheduled for the end of 2027.

Further reading

For broader context on energy infrastructure, see Oil and Gas coverage on Wisevoter.