Lyra Energy Starts Construction on 126 MW Noko Solar

The South African solar project is the second to be realised through the Lyra renewable power trading platform.

Updated on Nov. 27, 2026 in Energy

Photorealistic view of rows of dark solar panels on steel racks across flat dry grassland under open sky, with construction equipment at the edge of the array.
Lyra Energy has started construction on the 126 MW Noko solar project in South Africa, the second project realized through its renewable trading platform. AI Illustration. Upload story photo >

Lyra Energy has begun construction of the 126 MW Noko solar project in South Africa. Scatec decided to withdraw the 288 MW Mercury solar project from the REIPPP programme and sell it to Lyra.

Why it matters

The move reflects growing demand for corporate offtake agreements at attractive returns, which Scatec says is driving its shift away from the state-run REIPPP programme. For South Africa, it adds to the pipeline of privately contracted renewable capacity supplying commercial and industrial customers.

Lyra currently has two solar projects under construction totalling 381 MW and one backlog project of 288 MW. Scatec will contribute approximately $13 million in equity to Noko and receive approximately $100 million in D&C revenues, while the wider financing and construction timetable beyond the 2028 operations target remains unstated.

The players

Scatec

Scatec is a Norwegian renewable energy company that develops, builds and operates solar and hydropower projects across several countries.

Lyra Energy

Lyra Energy is a renewable power trading platform jointly owned by Scatec and STANLIB Infrastructure Investments that sells electricity to commercial and industrial customers.

STANLIB Infrastructure Investments

STANLIB Infrastructure Investments is the infrastructure investment arm of the South African asset manager STANLIB and co-owns Lyra Energy.

Standard Bank

Standard Bank is one of South Africa's largest banks and is providing the non-recourse project debt for the Noko solar project.

The details

Lyra, a renewable power trading platform owned 50/50 by Scatec and STANLIB Infrastructure Investments, acquires Scatec-developed projects and advances them to construction once sufficient corporate offtake is secured. Scatec provides construction, operations and asset management services, and Standard Bank will provide the non-recourse project debt for Noko.

Timeline

  1. First half of 2027: Lyra expects to start construction on the Mercury project.

  2. First half of 2028: Commercial operations at the Noko project are expected.

Market Dynamics

Scatec's decision to pull the 288 MW Mercury project out of the REIPPP programme marks a shift from state-tendered procurement toward corporate offtake agreements. The move follows the same programme that first brought large-scale independent solar into South Africa's grid, now being partly bypassed in favour of private contracts.

Commercial and industrial customers in South Africa are the ones buying power from Lyra under multi-year PPAs, so the Noko and Mercury projects will shape the supply options available to them. The projects are not expected to supply households directly, and their output will reach buyers only once commercial operations begin in 2028.

The takeaway

Privately contracted corporate offtake is becoming a viable route for large solar projects in South Africa, and watching whether Mercury reaches construction in 2027 will show if the model holds beyond Noko.

What happens next

Lyra expects to start construction on the Mercury project in the first half of 2027, and Noko is expected to reach commercial operations in the first half of 2028.

Further reading

For more on the country's power sector, see Energy coverage on South Africa's renewable build-out.

Source note: This article includes information reported by Renewable Energy Magazine, at the heart of clean energy journalism.