Lyra Energy Closes Financing on Noko Solar Project
Scatec and STANLIB's joint venture reached financial close on a 126 MW solar project in South Africa, with construction now under way.
Updated on Nov. 26, 2026 in Energy

Lyra Energy, a 50/50 joint venture between Scatec and STANLIB Infrastructure Investments, has reached financial close on the 126 MW Noko solar project in South Africa. Construction is under way, and Standard Bank will provide non-recourse project debt.
Why it matters
Scatec withdrew its 288 MW Mercury project from the REIPPPP programme, citing growing demand for corporate offtake agreements at attractive returns. Lyra supplies electricity to commercial and industrial customers in South Africa under multi-year power purchase agreements, so the move shifts how renewable capacity is financed and sold in South Africa.
Lyra Energy has 381 MW of solar under construction across two projects, with a further 288 MW in its backlog. Scatec will contribute about US$13 million in equity to Noko, while the total project cost and offtake pricing were not disclosed.
The players
Scatec
Scatec is a Norwegian renewable energy company that develops, builds and operates solar and hydro power projects across emerging markets, including South Africa.
Lyra Energy
Lyra Energy is a renewable energy platform jointly owned by Scatec and STANLIB Infrastructure Investments that acquires and builds solar projects in South Africa.
STANLIB Infrastructure Investments
STANLIB Infrastructure Investments is the infrastructure investment arm of the STANLIB asset management group, a South African investment manager.
Standard Bank
Standard Bank is one of Africa's largest banking groups and a major lender to large-scale energy and infrastructure projects in South Africa.
The details
Lyra acquires projects developed by Scatec and moves them into construction once enough corporate offtake has been secured. Noko is the second project realised through the Lyra platform, and Scatec expects to receive about US$100 million in design and construction revenues from it.
Timeline
Lyra expects to begin construction of the Mercury project in the first half of 2027.
Commercial operations at the Noko solar project are expected in the first half of 2028.
Market Dynamics
Scatec's decision to pull the 288 MW Mercury project from the REIPPPP programme marks a shift from state-run tenders toward privately contracted corporate offtake in South Africa. The move reflects the programme's role as the country's main renewable procurement route, which developers are now bypassing for higher returns.
Because Lyra sells electricity to commercial and industrial customers under multi-year agreements, the projects add renewable supply to the businesses that buy from it rather than to the national grid directly. The shift also means more South African power may be contracted privately, which affects how industrial electricity buyers secure supply.
The takeaway
Private corporate offtake is becoming a viable alternative to state tenders for South African solar developers, a trend that could accelerate as more projects seek returns beyond the national programme. Watch whether Mercury reaches construction in 2027 as a test of that model.
What happens next
Lyra expects to start construction of the 288 MW Mercury project in the first half of 2027, and Noko is expected to reach commercial operations in the first half of 2028.