Utility Board Approves Whispering Oak Sewer Bid

The Morgantown Utility Board unanimously awarded a $664,931 sanitary sewer contract to BC Allen Company for a Cheat Lake-area development.

Updated on Nov. 23, 2026 in Business

Utility Board Approves Whispering Oak Sewer Bid

Live Poll

Should developers pay the full cost of new sewer infrastructure for their projects?

The Morgantown Utility Board unanimously approved a bid from BC Allen Company, the lowest qualified bidder, for Phase II of the Whispering Oak sanitary sewer project. The bid amount is $664,931, and the developer of the Whispering Oak Development will pay for and reimburse the cost.

Why it matters

The project extends sanitary sewer service to the Whispering Oak Development in the Cheat Lake area, supporting new residential connections in Morgantown's utility service area. Approval moves the development's wastewater infrastructure forward while shifting the construction cost to the developer.

The winning bid of $664,931 covers 3,572 linear feet of gravity sewer line, 33 manholes and service connections for 75 properties, according to the board's approval. Other bid amounts and the exact completion date were not specified in the approval.

The players

Morgantown Utility Board

The Morgantown Utility Board is the municipal body that oversees water and sewer infrastructure and approves contracts for the Morgantown, West Virginia, utility system.

BC Allen Company

BC Allen Company is a contractor that submitted the lowest qualified bid to build the Whispering Oak Phase II sanitary sewer line.

The details

Bids for the project were opened on November 5, 2026, and the board approved the BC Allen Company bid on November 22, 2026. The Phase II work includes 27 standard manholes near the Cheat Road area, along with doghouse and drop manholes.

Timeline

  1. November 5, 2026: Bids for the Whispering Oak Phase II project were opened.

  2. November 22, 2026: The Morgantown Utility Board approved the BC Allen Company bid.

  3. End of 2027: Contractors are expected to complete the sewer project.

Market Landscape

The approval follows the Morgantown Utility Board's practice of requiring developers to fund and reimburse sewer extensions that serve new subdivisions, shifting infrastructure costs away from existing ratepayers. The arrangement positions the Cheat Lake corridor for continued residential growth on the existing sewer network.

Residents and businesses in the Cheat Lake area will not see a direct cost from this contract, since the developer pays for and reimburses the project. The extended sewer line will allow the Whispering Oak Development's homes to connect to public sanitary service.

The takeaway

Infrastructure costs for new development in Morgantown are being carried by the developers who benefit from them. Watching how the board handles similar extensions can show how growth is paid for in the Cheat Lake area.

Further reading

For more on local infrastructure, see Utilities coverage in Morgantown.

Source note: This article includes information reported by WAJR.

Live Poll

Should developers pay the full cost of new sewer infrastructure for their projects?