Morgantown Advances $46M Cheat Lake Plant Upgrade
Cheat Lake plant upgrades near completion as Morgantown Utility Board crews advance Cobun Creek sewer work.
Updated on Nov. 18, 2026 in Utilities

Morgantown Utility Board General Manager Mike McNulty reported progress on approximately $46 million in Cheat Lake Waste Water Treatment Plant upgrades at the board's Tuesday, November 17, 2026 meeting. The plant's treatment capacity is set to rise from 0.75 million to 1.75 million gallons per day.
Why it matters
The expanded capacity will serve Morgantown-area wastewater needs as the city's sewer system is upgraded. Completion of the electrical, control and pumping systems moves the plant closer to treating flows, which had been planned for November and are now expected in December.
The Cheat Lake plant's capacity is set to rise from 0.75 million to 1.75 million gallons per day, while the upgrades total about $46 million. Parotta Paving's Cobun Creek Phase II contract is just over $940,000, and the report does not state a firm finish date for that work.
The players
Morgantown Utility Board
The Morgantown Utility Board is the public utility that manages water and sewer services for the city of Morgantown, West Virginia, and oversees the Cheat Lake plant and the Cobun Creek sewer project.
Parotta Paving
Parotta Paving is a paving and utility construction contractor performing the Phase II installation of the Cobun Creek Interceptor under a contract with the Morgantown Utility Board.
The details
Contractors have completed electrical equipment installation, the plant's generator and most of its walls, and the control building is nearly finished. Parotta Paving has installed 1,530 feet of PVC gravity sewer pipe on Cobun Creek Phase II and has laid all piping around the Toyota dealership up to the White Park sewer connection. Contractors also restored about 920 feet of stream channel at Kelly Run.
Timeline
Tuesday, November 17, 2026: McNulty announces progress at the Morgantown Utility Board regular meeting.
November 2026: Original target for starting to treat flows at the new plant.
December 2026: Revised expected start of treating flows at the new plant.
The coming months: Majority of Cobun Creek Phase II expected to be completed.
Within the next few months: Full completion of Cobun Creek Interceptor Phase II expected.
Utilities Outlook
The Cheat Lake expansion, which more than doubles the plant's capacity from 0.75 to 1.75 million gallons per day, extends the Morgantown Utility Board's ongoing wastewater capital program. The Cobun Creek Phase II work continues that same program along the Don Knotts Boulevard corridor.
Morgantown residents served by the sewer system should see the Cheat Lake plant's expanded capacity come online around December, once flows are shifted to the new facility. Households in the Cobun Creek and White Park area may notice ongoing pipe and road work until the Phase II installation is finished.
The takeaway
Upgrades at the Cheat Lake plant more than double its treatment capacity, and the timeline now points to flows reaching the new facility in December. Residents should watch for the Cobun Creek Phase II completion, which the board expects within the next few months.
What happens next
Cheat Lake plant staff are expected to begin training on the new equipment in the coming weeks, and flows are expected to be treated at the new plant in December 2026.