County Approves $7.15 Million Health Department Renovation
Monongalia County Commission unanimously awarded the renovation contract for the health department's new White Birch Towers headquarters.
Updated on Nov. 10, 2026 in Home Renovation

The Monongalia County Commission unanimously approved a $7.15 million contract with a Morgantown-area construction firm to renovate the Monongalia County Health Department's new headquarters at White Birch Towers on Pineview Drive. The health department is relocating to the building by June 30, 2027.
Why it matters
The renovation prepares a new county health facility for residents who rely on its clinical, WIC and naloxone-related services. The project will convert five floors of the building to house these services and staff workspaces.
The project covers five floors, with phase one (floors two through five) targeted for substantial completion on June 1, 2027 and phase two (remaining floors two through four for staff workspaces) on August 1, 2027. The source does not state how the costs will be split between the two phases.
The players
Monongalia County Commission
The county's governing body, which unanimously approved the renovation contract for the health department's new headquarters.
Monongalia County Health Department
The county agency that provides public health services and is relocating its headquarters to White Birch Towers.
The details
The first phase focuses on spaces where staff interact directly with residents, including clinical dentistry on the fifth floor and the WIC unit and naloxone-related services on the second floor. The second phase completes staff workspaces on the second, third and fourth floors.
Timeline
Bids for the renovation contract were opened the week before the commission vote.
June 1, 2027: Phase one substantial completion and certificate of occupancy deadline.
June 30, 2027: The health department is expected to be out of its old building.
August 1, 2027: Phase two substantial completion and certificate of occupancy deadline.
Roadmap
Relocating a county health department into a multi-floor building and renovating it in two phases follows the standard procurement path for public facility projects. The phased timeline, with completion dates in mid-2027, sets the schedule for when residents will see services move to the new site.
Residents who use WIC, naloxone or dental services will eventually be served at the new White Birch Towers location once the first phase is finished. The move is scheduled for completion in 2027, so current services will continue at the existing site until then.
The takeaway
Public facility renovations of this size are typically scheduled in phases so essential services can keep operating, and residents should watch for the June 2027 move date to plan any visits.
What happens next
Phase one of the renovation is scheduled for substantial completion on June 1, 2027, and phase two on August 1, 2027, with the health department expected to move out of its old building by June 30, 2027.