Regulators Approve $2.7 Billion Gas Plant Plan
West Virginia's Public Service Commission OKs a 1.2-GW Maidsville plant tied to rising data center demand.
Updated on Nov. 24, 2026 in Utilities

Live Poll
Would you be willing to pay more on your electric bill for new data center power?
The West Virginia Public Service Commission approved a $2.7 billion plan by Monongahela Power and Potomac Edison Co. to build a 1.2-GW combined-cycle natural gas plant and add 70 MW of solar generation. A monthly surcharge will initially raise residential bills by $1.18, or 0.9%.
Why it matters
The project was prompted by an unnamed data center customer that requires 100 MW in 2028, rising to 1,012 MW by 2033, while the utility projects a capacity shortfall on its grid. For West Virginia ratepayers, the decision shifts the cost of new generation onto monthly bills before the plant is operating.
The approved plan carries a $2.7 billion price tag, with the 1.2-GW gas plant expected to cost $2.48 billion and the surcharge set to rise and fall every six months based on construction balances. Mon Power projects a 60 MW capacity shortfall in 2028 that grows to 2,194 MW by 2034, and the full long-term effect on bills is not yet defined.
The players
Monongahela Power
A West Virginia electric utility owned by FirstEnergy that serves customers across the state and proposed the Maidsville plant.
Potomac Edison Co.
A FirstEnergy subsidiary serving parts of West Virginia, Maryland and Virginia that co-sponsored the $2.7 billion plan with Monongahela Power.
FirstEnergy
A major Ohio-based investor-owned utility holding company whose subsidiaries include Monongahela Power and Potomac Edison.
Public Service Commission of West Virginia
The state regulator that reviews utility rates, plans and construction proposals and issued the November 17 approval.
The details
Monongahela Power and Potomac Edison will recover construction and financing costs through a monthly surcharge calculated every six months from construction-work-in-progress balances. The surcharge runs until the Maidsville Energy Center is included in base rates after it comes online, expected in late 2031.
Timeline
November 17, 2026: The Public Service Commission issued its decision approving the plan and surcharge.
2026: Mon Power projected a 2,997 MW summer peak.
2028: A data center customer requires an initial 100 MW, and a 60 MW shortfall is projected.
Late 2031: The gas plant is expected to come online and the surcharge moves into base rates.
2033: Data center load is expected to reach 1,012 MW.
Market Landscape
The approval follows a sharp rise in PJM Interconnection capacity prices that has pushed West Virginia utilities toward new generation to serve data center demand. The Maidsville plant positions Mon Power and Potomac Edison to add supply in a market where large industrial loads are reshaping regional resource planning.
Customers will see an initial $1.18 monthly increase on residential bills, with the surcharge recalculated every six months as construction costs change. The surcharge continues until the plant enters base rates, so the timing of bill changes depends on the late 2031 in-service date.
The takeaway
Residents should expect the costs of new generation to appear on monthly bills well before the plant produces power, so tracking future surcharge recalculations is the most direct way to understand the household impact.
Further reading
For related coverage, explore Utilities news from across West Virginia.
Source note: This article includes information reported by Utility Dive.