AG Joins Fight Over $145M Winter Storm Costs
West Virginia's attorney general has intervened in a federal energy proceeding backing Mon Power's effort to keep storm-related charges from reaching state electric customers.
Updated on Nov. 17, 2026 in Utilities

Live Poll
Should utility costs from winter storms be passed on to your household bill?
West Virginia Attorney General JB McCuskey intervened in a federal energy regulatory proceeding supporting Mon Power. Mon Power filed a complaint with the Federal Energy Regulatory Commission against PJM Interconnection in October over approximately $145 million in Winter Storm Fern costs.
Why it matters
The dispute determines whether roughly $145 million in storm-related wholesale power costs are passed on to West Virginia electric customers. Mon Power alleges PJM's advance scheduling decisions during the January 2026 storm drove unusually high costs.
Approximately $145 million in Winter Storm Fern costs are at issue in the FERC complaint filed against PJM Interconnection. The complaint's allegations regarding PJM's advance scheduling decisions remain unresolved pending a federal regulatory ruling.
The players
Mon Power
Mon Power is an electric utility serving customers in West Virginia and is the party seeking to keep the Winter Storm Fern costs off customer bills.
PJM Interconnection
PJM Interconnection is the regional grid operator coordinating wholesale electricity across multiple Mid-Atlantic and Midwest states, including West Virginia.
JB McCuskey
JB McCuskey is the Attorney General of West Virginia, the state's chief legal officer.
The details
Attorney General JB McCuskey, based in Charleston, intervened in the federal proceeding to support Mon Power's effort to block the charges from being passed on to West Virginia electric customers. Mon Power filed its complaint with the Federal Energy Regulatory Commission against regional grid operator PJM Interconnection, alleging that PJM's advance scheduling decisions during the January 2026 storm produced unusually high wholesale power costs.
Timeline
January 2026: Winter Storm Fern occurs and PJM advance scheduling decisions take effect.
October 2026: Mon Power files its complaint with FERC against PJM Interconnection.
November 17, 2026: The attorney general's intervention is reported.
Market Landscape
Complaints filed with FERC under the Federal Power Act are the standard route for utilities contesting wholesale charges set through regional grid operators like PJM. The West Virginia case shows how state attorneys general increasingly enter these proceedings to defend ratepayers from cost pass-throughs.
If the FERC rules against Mon Power, the roughly $145 million in Winter Storm Fern costs could appear on West Virginia electric bills. The outcome of the complaint will determine whether customers absorb those charges.
The takeaway
Regional grid decisions can reach household electric bills long after a storm ends. Customers in affected areas may want to watch the FERC docket to see how these costs are ultimately allocated.