District Gets Lowest Bid for Oshkosh Middle School
The Oshkosh school district received a $69.2 million low bid for a new west side middle school budgeted at $88 million.
Updated on Nov. 17, 2026 in Secondary Education

Live Poll
Do you trust your local school district to manage construction spending responsibly?
The Oshkosh school district received the lowest bid of $69.2 million for a new west side middle school budgeted at $88 million. The project is the largest in the district's $197.8 million referendum plan, which voters approved last year.
Why it matters
The district is consolidating from 20 schools to 15 because of declining enrollment, and the new building will serve up to 680 students in grades 6-8. Savings below the budgeted amount would reduce the taxes the district levies for referendum projects.
The lowest bid of $69.2 million came in $18.8 million below the $88 million budget for the middle school, which is part of a $197.8 million referendum plan. Final cost figures are not expected for about two years.
The players
Oshkosh School District
The public school district serving Oshkosh, Wisconsin, responsible for the referendum projects and the consolidation of its schools.
The details
The new middle school will be built on the site of the former Shapiro STEM Academy on West 18th Avenue and will serve up to 680 students in grades 6-8. The referendum plan also includes a performing arts center at Oshkosh North High School projected to cost about $5 million, and money must be spent only on projects within the referendum's scope.
Timeline
Last year: Voters approved the $197.8 million referendum plan.
December 2: The School Board will select the school name from three finalists.
2028-29: The new west side middle school is scheduled to open.
Roadmap
The consolidation from 20 schools to 15 follows statewide enrollment declines that have pushed Wisconsin districts to close or merge buildings. Oshkosh is reshaping its facilities to match a smaller student population while investing in newer schools.
Families with students in the Perry Tipler area should note that 75% of those students will move to the new school. The school name and opening timeline are set for the coming years, so parents can plan for the 2028-29 transition.
The takeaway
Lower-than-expected bids can free referendum money for other projects, but the district will not confirm final savings for about two years. Residents should watch the school name vote and construction milestones leading to the 2028-29 opening.
What happens next
The School Board will select the name for the new middle school from three finalists, Lewis Hine, Paul Poberezny, and Quarry Park, on December 2.
Further reading
Explore more about Secondary Education in Oshkosh for context on local school planning.