Roanoke to Hold Wasena Bridge Opening Nov. 30
The $50 million replacement bridge linking Wasena and Old Southwest is set for an open ceremony next month.
Updated on Nov. 16, 2026 in Openings & Closings

The City of Roanoke has scheduled an open ceremony for the replacement Wasena Bridge at 8:30 a.m. on Nov. 30, 2026. City Manager Valmarie Turner announced the event during Monday's city council meeting.
Why it matters
The new bridge reconnects the Wasena and Old Southwest neighborhoods, which were cut off during construction that began in spring 2024. Its completion ends a project delayed by a winter snow storm and two storms that damaged the temporary bridge.
The $50 million project replaced a bridge built in 1938, and the nearby Green Goat reports a 30% loss in business since construction began. It is not yet known how much business will recover once the bridge reopens.
The players
Valmarie Turner
Valmarie Turner is the City Manager of Roanoke, responsible for the city's administrative operations.
Joe Cobb
Joe Cobb is a public official referenced in the reporting on the Wasena Bridge project.
The details
The new bridge includes overlook areas on both ends, sidewalks, and designated bike lanes. Construction also diverted the Roanoke River Greenway and cut off the connection between the two neighborhoods.
Timeline
Spring 2024: Crews began replacing the 1938 Wasena Bridge.
Last winter: A snow storm shut down bridge work for one week.
Nov. 30, 2026, 8:30 a.m.: Scheduled open ceremony for the Wasena Bridge.
Openings & Closings
The Wasena Bridge replacement closes the chapter on a 1938 crossing that linked two Roanoke neighborhoods for nearly nine decades. Its reopening restores a route that construction had severed since 2024, returning the bridge to its original role in the city.
Drivers, cyclists, and pedestrians will regain a direct route between the Wasena and Old Southwest neighborhoods once the bridge opens. Residents and visitors who used the Roanoke River Greenway can expect it to be restored after construction diversions end.
The takeaway
The Wasena Bridge ceremony marks the end of a multi-year rebuild that cut off a neighborhood connection, so local businesses and commuters should watch for the reopening date.
What happens next
The open ceremony for the Wasena Bridge is scheduled for 8:30 a.m. on Nov. 30, 2026.
Further reading
For more on other local developments, browse Openings & Closings in Roanoke.
Source note: This article includes information reported by Roanoke Times.










