Rail Authority Shows New Alternate Routes
California's high-speed rail agency presented three alternate alignments to Los Banos residents as it seeks to lower costs.
Updated on Nov. 17, 2026 in Utilities

Live Poll
Would you support a high-speed rail route through your area even if it cost local land?
The California High-Speed Rail Authority showed three new potential route alignments to 48 residents at a Nov. 5 meeting in Los Banos. The alternatives are being considered as the Authority looks to reduce the cost of a route that currently relies on a 15-mile tunnel through Pacheco Pass.
Why it matters
The approved route's tunnel accounts for most of the $21 billion cost of the Gilroy-to-west-of-Merced segment, so changes to the alignment could significantly affect the project's budget. Alternatives that pass under French's Pass would encroach on Los Banos' sphere of influence, a concern for residents of the city and the wider San Joaquin Valley.
Tunneling costs roughly $1 billion per mile, and the approved Gilroy-to-Merced segment's $21 billion price tag is driven largely by its 15-mile Pacheco Pass tunnel. The Authority has not yet determined how much the alternate alignments could save.
The players
California High-Speed Rail Authority
The state agency responsible for planning and building California's high-speed rail system, which is redesigning its route to reduce costs.
The details
The Authority showed three new alignments to residents: Alt Five follows the adopted route but is steeper to reduce tunneling, while Alts Six and Seven curve south after Los Banos, combine where Los Banos Creek splits, and tunnel roughly four miles under French's Pass before descending to Gilroy. New technology allows trains to maintain a 220 MPH target speed on a 3 percent grade, and the Authority plans to use single-track wherever possible.
Timeline
Nov. 5, 2026: Scoping meeting held at the Los Banos Community Center presenting the alternate routes.
Early to mid-2027: Draft Environmental Impact Report expected to be released.
Late 2027: Final Environmental Impact Report expected to be released and certified.
Roadmap
The alternatives trade the approved route's 15-mile Pacheco Pass tunnel for steeper grades made possible by newer propulsion technology that allows a 3 percent grade, up from 1.5 percent. The redesign is a departure from the originally approved alignment, which relied on tunneling at roughly $1 billion per mile.
Residents of Los Banos and nearby communities could see the rail alignment move closer to or through their sphere of influence, depending on which alternative is adopted. The final route will also shape the project's cost and timing, which affects how long the rail line takes to reach the region.
The takeaway
Route choices now being weighed could reshape both the cost and the local footprint of California's high-speed rail line. Following the draft Environmental Impact Report will show which alignment the Authority moves forward with.
What happens next
A draft Environmental Impact Report is expected in early to mid-2027, followed by a Final EIR expected to be released and certified in late 2027. The Authority also plans to release an app letting the public view alignments around the time the draft EIR is completed.
Further reading
For more on how infrastructure projects are funded and built, explore Utilities coverage.
Source note: This article includes information reported by The West Side Index & Gustine Press-Standard.