Coastal Virginia Offshore Wind Project Reaches 85% Completion
Dominion Energy maintains its project budget of $11.65 billion as installation work progresses on the massive wind farm.
Updated on Oct. 30, 2026 in Current Conditions

Live Poll
Do you support the continued development of large-scale offshore wind energy projects?
The Coastal Virginia Offshore Wind project is now 85% complete, with 44 wind turbines installed and generating over 640 megawatts of capacity. Dominion Energy remains on track to finalize the project by the end of 2027.
Why it matters
The progress of this project is a critical indicator for the transition toward renewable energy infrastructure in Virginia. Reaching this milestone confirms that the utility company is maintaining its financial targets while scaling up significant power generation capacity for the state.
The project has successfully installed 44 turbines with a capacity exceeding 640 megawatts, while work has now begun on the 45th unit. The total budget holds at $11.65 billion, which includes $123 million in currently unused contingency funds.
The players
Dominion Energy
An energy company serving millions of customers that is the primary developer of the Coastal Virginia Offshore Wind project.
The details
Installation progress rose from 81% earlier in the year, despite recent slowdowns in September and October caused by weather conditions and maintenance requirements for the Charybdis vessel. Dominion Energy expects to energize the final offshore substation by the end of 2026.
Timeline
September 30, 2026: Quarterly earnings period concluded.
October 30, 2026: Project completion reached 85%.
Year-end 2026: Scheduled energization of the final offshore substation.
End of 2027: Targeted date for total project completion.
Seasonal Patterns
The project's progress serves as a primary driver in meeting the renewable mandates established by the Virginia Clean Economy Act. This initiative represents a massive increase in offshore generation capacity compared to historical energy output patterns in the state.
The progress of this wind farm has no immediate impact on local electricity pricing or grid reliability for residential consumers. Residents can expect the project to remain a focal point for long-term state energy capacity planning through 2027.
The takeaway
Dominion Energy continues to meet its primary infrastructure milestones despite maintenance-related slowdowns in turbine installation. Stakeholders should monitor the end-of-year energization of the final substation as a key indicator for project finalization in 2027.
What happens next
Dominion Energy is scheduled to energize the third and final offshore substation by the end of 2026.