Lydian Battery in Utah Starts Operating
A 150-MW standalone battery beside a 525-MW solar plant in Utah County now supplies contracted power to PacifiCorp.
Updated on Nov. 10, 2026 in Data Centers

Live Poll
Do you expect your electricity bills to rise over the next few years?
Lydian Energy's Faraday battery in Utah County began commercial operation on Sept. 18, 2026. The four-hour lithium iron phosphate system delivers 600 MWh of contracted capacity to PacifiCorp.
Why it matters
The battery is contracted through Rocky Mountain Power's Schedule 34 in support of Meta's Eagle Mountain data center, linking large-scale storage to the energy demands of data centers in Utah. Its placement beside an existing solar plant shows how storage can be added to current generation without a separate grid connection.
The system is a standalone lithium iron phosphate battery rated 150 MW with four-hour duration, providing 600 MWh of storage on roughly eight acres, or about 75 MWh per acre. Lydian has not named the battery supplier or disclosed the project cost.
The players
Lydian Energy
Lydian Energy is a developer of solar and battery storage projects that now reports a 6.0-GW portfolio, up from 4.4 GW in February.
PacifiCorp
PacifiCorp is a regional electric utility whose Rocky Mountain Power division operates the Schedule 34 tariff under which the battery's output is contracted.
Meta
Meta is the technology company whose Eagle Mountain data center in Utah is supported by the battery's contracted capacity.
The details
The battery shares the adjacent solar plant's substation and grid connection, and it was built in about 10 months from mobilization to commercial operation. Lydian announced $689 million in financing from CIBC and MUFG in February 2026 covering this project and two solar projects in New Mexico and Texas.
Timeline
February 2026: Lydian announced $689 million in financing from CIBC and MUFG.
June 2026: A wildfire threatened the project area.
Sept. 18, 2026: The battery began operating.
Nov. 10, 2026: Lydian issued a statement on commercial operation.
Fourth quarter 2028: Targeted in-service date for a second battery of up to 375 MW / 1,500 MWh at the same site.
Infrastructure Shift
The project is contracted under Rocky Mountain Power's Schedule 34, a tariff that lets the utility buy clean energy for Utah customers with a peak load of at least 5,000 kW. Its use here to support a standalone battery tied to Meta's Eagle Mountain data center extends that tariff beyond solar procurement.
The battery adds contracted storage capacity to the PacifiCorp system that supports the power needs of Meta's Eagle Mountain data center. Storage paired with solar can supply electricity when generation falls, which bears on how reliably the grid serves large loads in Utah.
The takeaway
Battery storage co-located with solar is becoming a practical way to firm up clean power for large loads. The Faraday project shows how a single grid connection can serve both generation and storage.
What happens next
Lydian is developing a second battery of up to 375 MW / 1,500 MWh at the same site, with a targeted in-service date in the fourth quarter of 2028.