Utilities Completes $7M Gruene Road Sewer Upgrade
New Braunfels Utilities finished a sewer main project in the Historic Gruene District that ended months of traffic disruptions along Gruene Road.
Updated on Nov. 18, 2026 in Utilities

New Braunfels Utilities completed the $7 million Gruene Road Sewer Main Rehabilitation and Relocation Project in the Historic Gruene District, ending months of traffic disruptions. Construction ran from January 2026 until early November 2026.
Why it matters
The project upgraded aging wastewater infrastructure beneath the Historic Gruene District, adding capacity for wastewater flows and reducing the likelihood of problems tied to old pipes. Residents and businesses in New Braunfels gain more dependable service as a result.
The $7 million project enlarged a wastewater main from 12 inches to 18 inches, a 50% increase in diameter over the original line. The source does not report how the cost compares with prior NBU capital projects or whether the budget was exceeded.
The players
New Braunfels Utilities
New Braunfels Utilities is the municipally owned utility provider serving the city of New Braunfels, Texas, responsible for water and wastewater infrastructure.
The details
Crews replaced aging sewer lines crossing the Guadalupe River and installed a new odor-control unit. Lane restrictions, parking limitations and overnight closures were used along Gruene Road, Hunter Road and New Braunfels Street during construction.
Timeline
December 2025: Project first announced, with its construction timeline and traffic changes outlined.
January 2026: Construction began.
Early November 2026: Construction wrapped up.
November 13, 2026: New Braunfels Utilities announced the project's completion.
Utility Infrastructure
The Gruene Road project follows a pattern of replacing aging wastewater mains in established urban districts, upsizing older lines to handle more flow. It fits the broader effort by Texas municipal utilities to renew decades-old sewer infrastructure beneath historic neighborhoods.
Drivers on Gruene Road, Hunter Road and New Braunfels Street no longer face the lane restrictions, parking limitations and overnight closures that came with construction. Customers in the Historic Gruene District can expect more dependable wastewater service as the upgraded main takes over.
The takeaway
Upgrading aging wastewater mains before they fail is a cost-effective way to protect service in older neighborhoods. Residents of historic districts can watch for utility announcements about similar projects to plan around possible disruptions.
Further reading
Learn more about the work of Utilities across New Braunfels.
Source note: This article includes information reported by MySA.






