Last Energy Completes Reactor Building at Texas A&M
The small nuclear demonstration reactor is being built on Texas A&M University's RELLIS campus in Bryan, Texas.
Updated on Nov. 25, 2026 in Nuclear

Last Energy has completed the reactor building for a small nuclear reactor on Texas A&M University's RELLIS campus in Bryan. The company received Documented Safety Analysis from the Department of Energy in October, and the reactor was awaiting Department of Energy authorization to reach criticality in September.
Why it matters
The project is a test of whether scaled-down versions of existing pressurized water reactors can serve as proving grounds for larger units in Bryan and across Texas. Last Energy said its earlier problem was the business model rather than the reactor itself.
The reactor site sits about one mile from an existing reactor, and the campus has not built a reactor in more than three decades. Whether the demonstration unit will reach criticality on the schedule described has not been confirmed.
The players
Last Energy
Last Energy is the company building the small pressurized water reactor design on the Texas A&M campus.
Texas A&M University
Texas A&M University is the Bryan-based public research university hosting the reactor on its RELLIS campus.
Department of Energy
The U.S. Department of Energy is the federal agency responsible for safety oversight and authorization of the project.
The details
The PWR 5 is a smaller counterpart to the PWR 20 and will be housed below ground in a hermetically sealed steel container. Texas A&M has agreements with Kairos Power, Natura Resources, Terrestrial Energy, and Aalo Atomics, and the Department of Energy is responsible for safety oversight, with Texas A&M researchers helping review work on campus.
Timeline
January: Construction of the reactor building began.
Late August: Reactor building construction was completed.
September: The reactor was waiting on Department of Energy authorization to reach criticality.
October: Last Energy received Documented Safety Analysis from the Department of Energy.
The Big Picture
The demonstration reactor applies the design of the existing U.S. pressurized water reactor fleet at a smaller scale, testing whether that approach can be built and operated before a larger unit is installed alongside it. Its progress will show whether small reactors built on this model can move from demonstration to commercial use.
Bryan residents living near the RELLIS campus are close to a new reactor site about one mile from an existing one. The project's safety oversight is led by the Department of Energy with Texas A&M researchers reviewing the work on campus.
The takeaway
A demonstration reactor on a university campus shows how smaller nuclear designs can be tested under federal oversight before wider deployment. Readers interested in the technology can follow its progress through the Department of Energy authorization process.
What happens next
The reactor is waiting on Department of Energy authorization to reach criticality, and the larger PWR 20 is planned to be installed alongside the PWR 5 after its initial role.