Bryan Utilities Begins SH 21 Power Line Work

Bryan Texas Utilities starts relocating power lines near SH 21 and the SH 6 bypass, with lane closures beginning November 30, 2026.

Updated on Nov. 25, 2026 in Business

Weathered wooden utility poles and cables line an empty flat highway shoulder under overcast daylight, with one pole newly set in a gravel trench.
Bryan Texas Utilities crews begin relocating power lines near East SH 21 and the SH 6 bypass on Monday, November 30, 2026, in the first of four phases. AI Illustration. Upload story photo >

Bryan Texas Utilities crews will relocate power lines near the intersection of East SH 21 and the SH 6 bypass in four phases, beginning Monday, November 30, 2026. Phase one includes daily closures of one westbound SH 21 lane between Carrabba Street and Bluebonnet Street from 8:30 a.m. to 3 p.m.

Why it matters

The relocation prepares for future phases of the Texas Department of Transportation's Big 6 Project, which motorists in Bryan will encounter through intermittent lane closures and detours. Drivers on SH 21 and Nuches Lane should expect delays during the work.

Phase two closes one eastbound SH 21 lane from 300 feet west of Bluebonnet Street to 100 feet east of Nuches Lane between 8:30 a.m. and 3 p.m. daily. Phase four detours the northbound Nuches Lane lane from Old Kurten Road to SH 21 from 8 a.m. to 3 p.m.

The players

Bryan Texas Utilities

The municipal utility serving the City of Bryan, Texas, which is conducting the power line relocation work.

Texas Department of Transportation

The state agency overseeing the Big 6 Project, of which this power line relocation is a part.

The details

Phase three includes rolling stops of all SH 21 lanes at Bluebonnet Street, made in intervals as needed to limit backups. Bryan Texas Utilities will post updates on its social media pages when crews move to the next phase.

Timeline

  1. Monday, November 30, 2026: Phase one lane closures on SH 21 begin.

  2. Weekdays, 8:30 a.m. to 3 p.m.: Daily lane closures during phases one and two.

  3. Weekdays, 8 a.m. to 3 p.m.: Daily Nuches Lane detour during phase four.

Roadmap

The power line relocation is a preparatory step for future phases of the Texas Department of Transportation's Big 6 Project. Utility relocations like this one typically precede roadway construction to avoid conflicts once major work begins.

Drivers using SH 21 through Bryan should plan for single-lane closures between 8:30 a.m. and 3 p.m. on weekdays. Nuches Lane users should expect a northbound detour from Old Kurten Road to SH 21 between 8 a.m. and 3 p.m.

The takeaway

Plan commute times around weekday lane closures on SH 21 and the Nuches Lane detour until the relocation work is complete.

What happens next

Phase one lane closures begin Monday, November 30, 2026, with later phases to follow as crews advance.

Further reading

For more on local service work, see Utilities coverage for Bryan.

Source note: This article includes information reported by FOX 44.