Standard Lithium, Equinor Advance Texas Lithium Project

A preliminary economic assessment outlines a 20-year lithium carbonate operation in East Texas's Smackover Formation.

Updated on Nov. 26, 2026 in Science

Isometric editorial illustration of plain cylindrical storage tanks, a pipeline, and a low processing structure set in a flat pine clearing.
Standard Lithium and Equinor released a preliminary economic assessment for a 20-year East Texas project targeting up to 70,000 tonnes of lithium carbonate a year. AI Illustration. Upload story photo >

Standard Lithium and Equinor filed a Preliminary Economic Assessment Technical Report for the Franklin Project on SEDAR+. The assessment contemplates annual production of up to 70,000 tonnes of battery-quality lithium carbonate.

Why it matters

The report points to a potential domestic source of battery-grade lithium in Texas, a material central to electric vehicle and energy storage supply chains. The partnership plans to advance the project to a Preliminary Feasibility Study.

The assessment models a 20-year operating life producing 1.29 million tonnes of lithium carbonate, from brine starting at 562 mg/L lithium with an average of 515 mg/L, with average annual cash operating cost of $4,226/t and capital intensity of $49,945/t. Whether direct lithium extraction will perform at these concentrations across the full project area remains under testing.

The players

Standard Lithium

Standard Lithium is a lithium exploration and development company that is advancing direct lithium extraction projects in the United States.

Equinor

Equinor is a Norwegian multinational energy company that has expanded into lithium development through partnership with Standard Lithium.

The details

The Franklin Project is the partnership's first defined project area in East Texas's Smackover Formation, and the resource was upgraded and upsized as a Mineral Resource. The partnership draws on insights from Standard Lithium's Demonstration Plant and its South West Arkansas Project in direct lithium extraction testing of the project brine.

Timeline

  1. Initial lithium production could begin in the early 2030's.

  2. Potash was designated a U.S. critical mineral in 2025.

  3. The PEA Technical Report was filed on SEDAR+ on November 26, 2026.

Season Trajectory

The Franklin Project extends the Smackover Formation brine lithium development that Standard Lithium has pursued in South West Arkansas into East Texas. The partnership's direct lithium extraction approach positions Texas as a possible next domestic lithium source alongside Arkansas.

Direct lithium extraction from Texas brine could eventually supply battery-grade lithium carbonate for electric vehicles and grid storage. Commercialization depends on completing further feasibility work before any production begins in the early 2030's.

The takeaway

Texas's emerging lithium brine projects could become a meaningful domestic source of battery materials if the preliminary economics hold through feasibility studies. Readers following energy and critical minerals should watch for the Preliminary Feasibility Study that the partnership plans next.

Further reading

Explore more on Energy developments shaping Texas's critical mineral supply.

Source note: This article includes information reported by Magnolia Reporter.