Core Scientific Files $1.3B Hunt County Data Center

Telios Quinlan One, LLC filed the 341,325 sq ft Core Scientific - Hunt project with Texas regulators.

Updated on Nov. 16, 2026 in Data Centers

Isometric editorial illustration of a windowless concrete building and steel substation towers on flat, dry prairie under even daylight.
Telios Quinlan One, LLC filed with Texas regulators for a $1.3 billion Core Scientific data center in Hunt County, with AMD leasing 110MW of the campus. AI Illustration. Upload story photo >

Telios Quinlan One, LLC has filed with the Texas Department of Licensing and Regulation for the Core Scientific - Hunt data center project in Quinlan, Hunt County. The $1.3 billion core and shell building would sit on a 265-acre site about 53 miles northeast of Dallas.

Why it matters

The project adds large-scale data center capacity in Texas, with up to 285MW of leasable capacity on the campus. AMD has agreed to lease 110MW at the site as part of a wider leasing agreement with Core Scientific.

The campus can support up to 285MW of leasable capacity on a 430MW gross basis, with an on-site substation planned and the site located close to Acciona Energia's 190MW Cunningham battery energy storage system. AMD's 110MW lease is set against that total, while the timing of the substation's completion has not been specified.

The players

Core Scientific

Core Scientific is a publicly traded digital infrastructure company that operates and hosts cryptocurrency mining and high-performance computing facilities across several U.S. states.

AMD

Advanced Micro Devices is a major American semiconductor company that designs CPUs and GPUs for computing and data center markets.

Acciona Energia

Acciona Energia is the renewable energy arm of the Spanish infrastructure group Acciona, developing wind, solar and battery storage projects.

The details

Core Scientific acquired Telios Quinlan One LLC for $232.5 million to obtain the site, which is mostly vacant land at 4852 County Road 3507 in Quinlan. Construction on the 341,325 sq ft building is projected to run from November 2026 until September 2028.

Timeline

  1. March 2026: Core Scientific announced its acquisition of the 265-acre Hunt County site.

  2. Earlier in 2026: Belltown Power withdrew its Quinlan project application.

  3. November 2026: Construction on the $1.3 billion project is set to begin.

  4. 2027: The site could begin energizing.

  5. September 2028: Construction is scheduled to finish.

Tech Race

The Hunt County campus is planned close to Acciona Energia's 190MW Cunningham battery energy storage system, placing new data center load alongside existing large-scale storage in the same area. The project's on-site substation and 430MW gross capacity show the scale developers are pursuing in Texas as AI and computing demand grows.

For Texans living near Quinlan, the project brings a large construction effort and a new industrial campus to Hunt County from late 2026 through 2028. The planned substation and grid connection will shape local power infrastructure as the site comes online.

The takeaway

The Hunt County project shows how large data center campuses are being sited alongside power infrastructure in Texas. Readers tracking regional energy and computing capacity should watch the 2027 energizing milestone.

What happens next

Construction is scheduled to begin in November 2026, with the site projected to start energizing in 2027 and reach full power by 2029.