Energy Vault Closes $78M Financing for Texas Battery
The non-recourse financing supports construction of the 150-MW SOSA Energy Center in Madison County.
Updated on Nov. 23, 2026 in Science

Energy Vault Holdings closed $78 million of construction and bridge financing for the SOSA Energy Center, a 150-MW / 300-MWh battery storage project in Madison County, Texas. An $80 million preferred equity investment is committed and will repay the bridge financing at project completion.
Why it matters
The project adds grid storage capacity in ERCOT, where installed energy storage stood at 22,072 MW in November 2026. SOSA will sell power and ancillary services on a merchant basis in the ERCOT North market, without a contracted buyer for now.
The figures come from a company press release announcing the financing, with the project's 150 MW capacity and 300 MWh energy capacity set against 22,072 MW of installed ERCOT storage. The lender, loan terms, OIC draw size and battery supplier remain undisclosed.
The players
Energy Vault Holdings
Energy Vault Holdings is a publicly traded energy storage company that develops, builds and operates battery storage projects.
Cory Magnuson
Cory Magnuson is a public official quoted in connection with the SOSA Energy Center project.
The details
Energy Vault performs the engineering, procurement and construction itself, and civil work is complete with a substation installed. The incremental equity is covered by an additional draw on the company's existing OIC preferred facility, and the financing is non-recourse.
Timeline
Q4 2025: Construction started on SOSA Energy Center.
November 23, 2026: Energy Vault announced the non-recourse financing.
Coming months: Major equipment is due on site.
Q3 2027: Commercial operation of SOSA is expected.
Grid Context
The 150-MW SOSA project adds to ERCOT's installed storage base of 22,072 MW reported in November 2026. Its merchant sales into ERCOT North expose it to the market prices that storage capacity in the state now competes on.
For Texas electricity customers, the project adds battery capacity to the ERCOT North market that can supply power and ancillary services. The project is expected to bring $9.3 million in tax revenue over 10 years to local entities, including North Zulch ISD, and create 65 construction jobs.
The takeaway
Storage projects like SOSA are increasingly financed on merchant exposure rather than contracted revenue, so their returns depend on market prices in ERCOT. The company expects recurring EBITDA margins of about 65% to 75% and $250 million to $300 million-plus of long-term revenue, though those are projections.
What happens next
Major equipment is due on site in the coming months, and commercial operation of SOSA Energy Center is expected in the third quarter of 2027.
Further reading
For broader context on grid-scale power, explore more Energy coverage.
Source note: This article includes information reported by List.