Charge Power has been awarded commissioning management for two battery energy storage system projects in Texas. Together the projects add 290 MW / 580 MWh of storage capacity to the ERCOT grid, and both are onboarding the WARAM platform for project governance, due diligence and compliance.
Why it matters
Battery storage is growing rapidly on the ERCOT grid, and commissioning support helps projects energize on time and begin earning from day one. Charge Power says its role is to close gaps in project delivery.
The two projects are a 150 MW / 300 MWh system and a 140 MW / 280 MWh system, which together add 290 MW / 580 MWh to the ERCOT grid. Charge Power says it has commissioned 3 GW / 7 GWh of storage since 2022, though the source does not detail the award value.
The players
Charge Power Inc.
A small business that integrates EPC contractors, engineers and suppliers to commission battery energy storage projects, with offices in Austin, Texas and Toronto.
The details
Charge Power will integrate EPC contractors, project engineers, suppliers, documentation and the ERCOT interconnection checklist on the owner's behalf. Both projects are onboarding WARAM, a platform that links physical energy-asset requirements to the evidence proving them, and both are expected to reach commercial operation in 2027.
Timeline
2022: Charge Power founded.
2025: ERCOT battery capacity grew 76%.
End of June 2026: ERCOT battery capacity reached 16.5 GW / 28.8 GWh.
November 16, 2026: Charge Power announced the two Texas project awards.
2027: Both projects expected to reach commercial operation.
Roadmap
Texas battery capacity has roughly doubled each year from 2020 through 2024, and grew another 76% in 2025 according to Modo Energy's ERCOT tracking. The two Charge Power projects extend that buildout, adding 290 MW / 580 MWh to a grid that reached 16.5 GW / 28.8 GWh by June 2026.
Texas electricity consumers may see savings from storage, which an American Clean Power Association analysis estimates have exceeded $750 million since 2023. Storage projects like these can help the grid meet demand during peak periods.
The takeaway
Battery storage is becoming a larger part of Texas's grid, and the projects' on-time commissioning will determine how quickly that capacity starts serving consumers. Tracking commercial operation dates in 2027 will show whether the capacity additions arrive as planned.
What happens next
Both projects are expected to reach commercial operation in 2027.