Texas Approves First Wellfield at Upper Spring Creek
enCore Energy's South Texas uranium project receives its final wellfield permit needed for injection and recovery operations.
Updated on Nov. 19, 2026 in Science

The Texas Commission on Environmental Quality issued the Production Area Authorization for the first wellfield at enCore Energy's Upper Spring Creek In-Situ Recovery Uranium Project. The authorization is the final wellfield permit required for injection and recovery at the site, which was built ahead of approval.
Why it matters
The authorization moves the project toward full-scale uranium recovery in South Texas, a step that depends on the expected approval of a waste disposal well. It also shows how in-situ recovery projects advance through state permitting before routine production begins.
The uranium-mineralized sands sit within the Oakville Formation at typical depths of 300 to 450 feet below surface, a range the source does not compare against other South Texas projects. Full-scale operations remain contingent on the Waste Disposal Well approval the company expects in December.
The players
enCore Energy
A uranium company that owns the Upper Spring Creek project and reports its operations to investors and regulators.
Texas Commission on Environmental Quality
The state agency that issued the Production Area Authorization for the first wellfield at the Upper Spring Creek project.
The details
In-situ recovery dissolves uranium from underground sands through injected solution, which is then pumped back to the surface. Uranium-loaded resin from the Satellite Ion Exchange Plant is trucked to the Rosita Central Processing Plant, where it is processed into yellowcake. Excess saline water, known as the bleed stream, is disposed of through a permitted deep disposal well.
Timeline
December 2020: enCore Energy acquired the Upper Spring Creek project.
Before 2020: Signal Equities licensed and permitted the property as an in-situ recovery project.
November 19, 2026: The Texas Commission on Environmental Quality issued the first wellfield authorization.
December 2026: enCore Energy expects Waste Disposal Well approval.
Seasonal Patterns
The authorization follows the Texas permitting sequence for in-situ recovery projects, in which wellfield approval precedes the disposal well needed for full operations. The source offers no historical record of comparable Texas approvals, so the project's pace cannot be measured against prior wellfield timelines.
For South Texas residents near the project, the approval means in-situ uranium recovery will move toward full production once the disposal well is cleared. The source does not describe local traffic, employment, or groundwater effects, so those impacts remain unconfirmed.
The takeaway
The first wellfield approval is a permitting milestone rather than the start of full production, which depends on the disposal well approval expected in December. Readers following South Texas uranium development should watch that decision as the next confirmed step.
What happens next
The company expects the Texas Commission on Environmental Quality to approve the Waste Disposal Well in December, after which the wellfield will move to full-scale operations.
Further reading
For background on the state's nuclear activity, see the Nuclear section.
Source note: This article includes information reported by Star Local.