Developers Face Delays Along I-35 Corridor
Financing, utility access and lengthy entitlement processes are slowing commercial projects between Austin and San Antonio.
Updated on Nov. 12, 2026 in Commercial

Live Poll
Do you think your community is growing in a good direction?
Developers along the I-35 corridor between Austin and San Antonio are facing project delays tied to financing challenges, limited utility access and lengthy entitlement processes. The corridor is one of the nation's most active commercial real estate development areas, according to a panel discussion at the Bisnow Central Texas Mega-Metro Summit in Kyle on Oct. 29.
Why it matters
Projects along the corridor must clear review processes across five or six jurisdictions, and equity and debt financing have become more conservative. For Texas, a state where growth is pushing demand for both housing and commercial space, these bottlenecks affect how quickly new retail, restaurants and mixed-use projects reach the market.
Kyle Park is a 100-acre mixed-use project with multifamily housing, restaurants and retail, with Dick's Sporting Goods and Barnes & Noble as confirmed tenants, while Schertz Station is a $65 million, 72-acre development that will house Home Depot and Cava. The panel did not provide a corridor-wide tally of delayed projects, and the extent of the setbacks remains unquantified.
The players
Bisnow
Bisnow is a commercial real estate news and events company that hosts regional industry summits.
Dick's Sporting Goods
Dick's Sporting Goods is a large American sporting goods retailer and a confirmed tenant of Kyle Park.
Barnes & Noble
Barnes & Noble is a national bookseller and a confirmed tenant of Kyle Park.
Home Depot
Home Depot is a major home improvement retailer slated to occupy space at Schertz Station.
Cava
Cava is a fast-casual Mediterranean restaurant chain slated to occupy space at Schertz Station.
The details
Panelists described off-site utility work that can set a project back one to two years when developers must bring power and water to sites miles from existing lines. Redesign loops, pricing revisions and plan changes have further lengthened the entitlement stage, which the panel said is a key source of delay.
Timeline
Oct. 29, 2025: Panel discussion at the Bisnow Central Texas Mega-Metro Summit in Kyle
Late 2027: Projected completion of the first phase of Kyle Park's five-year development timeline
2080: Projected annual water shortage of about 5 billion gallons east of I-35 in parts of Travis County
Market Landscape
Water supply pressure in the Austin region, driven by recurring drought and rapid population growth, is now shaping where commercial projects can practically be built along I-35. Developers who can secure utilities early gain a timing advantage over those who must extend lines to remote sites.
Anyone considering a commercial lease or purchase along the I-35 corridor should factor in possible utility and entitlement delays when estimating opening dates. Business owners planning to relocate may need to allow extra lead time before a new site is ready for occupancy.
The takeaway
Projects that secure utilities and entitlements early are better positioned to avoid multi-year delays. Buyers and tenants should ask developers directly about utility status and approval timelines before committing.
Further reading
For broader context, see Commercial listings across Texas.
Source note: This article includes information reported by Bisnow.