EPA Completes PCE Southeast Superfund Cleanup in York

The federal agency finished soil cleanup at the York site a decade earlier than anticipated, using thermal remediation.

Updated on Nov. 13, 2026 in Environmental

Isometric editorial illustration of bare steel well-heads and pipework on a concrete pad beside a plain cabinet and low brick rooftops, in muted slate, oxblood, and cream.
The EPA finished soil cleanup at the York PCE Southeast Superfund site on November 12, 2026, a decade ahead of schedule, and will now turn to groundwater. AI Illustration. Upload story photo >

Live Poll

Should federal agencies prioritize faster cleanup of contaminated sites in your community?

The U.S. Environmental Protection Agency has completed cleanup of the PCE Southeast Contamination Superfund site in York, a decade earlier than anticipated. The agency announced completion of Operable Unit 01 cleanup on November 12, 2026, and will now shift to restoration work and groundwater remediation.

Why it matters

The site was contaminated by PCE and TCE released by two former dry-cleaning businesses, which formed an underground plume near Seventh Street and North Platte Avenue. Completing soil cleanup moves the remaining effort toward groundwater, which the EPA says will now be the focus of remediation.

Soil sampling in October 2026 found PCE below 46 micrograms per kilogram and TCE at 36 micrograms across 10 locations at 5-foot depth intervals. Groundwater contamination remains under study, and the timeline for its cleanup was not specified.

The players

U.S. Environmental Protection Agency

The EPA is the federal agency responsible for environmental protection and the administration of the Superfund program for hazardous waste site cleanup.

The details

The EPA heated contaminated soil using in-situ thermal remediation, turning contaminants into vapors, after deeming soil removal and replacement more expensive, time-consuming and disruptive. The agency will next remove the thermal remediation system, work trailers and concrete, and then turn to contaminated groundwater.

Timeline

  1. 2011: EPA added the locations to its Superfund list.

  2. 2023: Soil cleanup of Operable Units 01 and 02 began, and EPA shifted to thermal remediation.

  3. 2025: Cleanup of Operable Unit 02 concluded.

  4. October 2026: EPA sampled soil at 10 spots across the site.

  5. November 12, 2026: EPA announced completion of Operable Unit 01 cleanup.

Big Picture

The cleanup operates under the CERCLA Superfund program, which requires long-term remediation of both soil and groundwater at listed sites. Completing the soil phase early leaves groundwater as the remaining obligation under that framework.

Nearby residents will see equipment and work trailers removed as the soil phase closes out. The shift to groundwater cleanup means the contamination underground near Seventh Street and North Platte Avenue remains a continuing concern.

The takeaway

Early completion of a Superfund soil remedy shows that thermal treatment can shorten timelines compared with removal and replacement, though groundwater work will set the pace of remaining cleanup.

What happens next

EPA will remove the thermal remediation system, work trailers and concrete, then begin groundwater cleanup at the site.

Further reading

For more on local hazardous-waste efforts, explore Environmental coverage tied to York.

Source note: This article includes information reported by JournalStar.