PennDOT Gets Bids for I-83 York Widening

Three contractors bid on the first phase of expanding Interstate 83 from three to six lanes in York, with the lowest bid at $213.3 million.

Updated on Nov. 12, 2026 in Business

Wide view of a concrete highway bridge spanning a creek through wooded farmland under overcast daylight, with new steel girders visible along the deck.
The Pennsylvania Department of Transportation received three bids for the first phase of widening Interstate 83 in York, with J.D. Eckman Inc. the apparent low bidder at $213.3 million. AI Illustration. Upload story photo >

The state Department of Transportation received three bids for the first phase of widening Interstate 83 in York, and J.D. Eckman Inc. of Chester County is the apparent low bidder at $213,307,621.45. The department is reviewing the information the firm submitted before any contract is awarded.

Why it matters

The project would expand a key York highway corridor and replace bridges over Codorus Creek, Mill Creek and Loucks Mill Road, affecting daily commuters for years. Multi-year reconstruction of interchanges planned through 2034 means York drivers should expect a long period of construction.

Bids ranged from $213,307,621.45 to $228,673,274.89 across three submissions for the first phase. The state has not yet confirmed whether the lowest bidder's paperwork meets contract requirements.

The players

Pennsylvania Department of Transportation (PennDOT)

The state agency that manages Pennsylvania's highways and received the bids for the Interstate 83 widening project.

J.D. Eckman Inc.

A Chester County contractor that is the apparent low bidder on the first phase of the Interstate 83 project.

The details

The first phase, known as the Codorus Creek bridge replacement, covers I-83 from south of the Route 30 interchange to south of the Eberts Lane bridge. Some work has already been completed, including a new I-83 North on-ramp from North George Street, and the wider project will eventually widen the highway from four to six lanes between the North George Street and Market Street interchanges.

Timeline

  1. Construction on the first phase is expected to begin in early 2027.

  2. Reconstruction of the Route 30 and North George Street interchanges is scheduled for 2029 through 2033.

  3. A makeover of the Market Street interchange is planned for 2030 through 2034.

Market Landscape

The three bids cluster between $213 million and $229 million, suggesting competitive pricing among the regional firms that bid on large Pennsylvania highway work. The spread between the lowest and highest bid is about $15 million, a narrow margin for a project of this size.

Drivers using I-83 through York should expect lane closures and detours once construction begins in early 2027. Commuters who rely on the North George Street and Market Street exits may face extended disruption through 2034 as interchanges are rebuilt.

The takeaway

Large highway projects like this one run for years, so commuters who plan ahead can reduce frustration by checking PennDOT updates and considering alternate routes before construction begins.

What happens next

The department is reviewing J.D. Eckman's bid, and if everything is in order the contract will be awarded to the firm, with construction expected to start in early 2027.