City Council Blocks Power Line Project in Forest Park

Portland General Electric's Harborton Reliability Project faces renewed opposition after a hearings officer's approval.

Updated on Nov. 24, 2026 in City Hall

City Council Blocks Power Line Project in Forest Park

Live Poll

Should Portland allow power lines through Forest Park despite tree and wetland losses?

Portland's hearings officer approved Portland General Electric's Harborton Reliability Project land use application, but the Forest Park Neighborhood Association says it intends to appeal again. The project would add power poles and 1,400 feet of new transmission line in Forest Park near Highway 30.

Why it matters

The project would affect 4.7 acres within Forest Park, remove 375 living trees and 18 dead trees, and impact two wetlands and two streams, making it a contested use of protected urban green space in Portland. Residents and conservation groups are weighing whether the revised settlement and mitigation terms adequately address those impacts.

The project would affect 4.7 acres within Forest Park and remove 375 living trees and 18 dead trees, with PGE proposing $5.5 million in mitigation funds. It remains unclear whether City Council will uphold the revised approval or whether further appeals will succeed.

The players

Portland General Electric

Portland General Electric is the investor-owned utility serving most of Oregon's Portland area and is the applicant for the Harborton Reliability Project.

Forest Park Neighborhood Association

The Forest Park Neighborhood Association is a community group representing residents near Oregon's Forest Park, which has repeatedly opposed the project's approval.

The details

The Portland hearings officer's approval followed a settlement between the city and PGE reached in July through mediation after an appeal to the Oregon Land Use Board of Appeals. The project would connect existing PGE lines with Bonneville Power Administration lines and destroy two wetlands, and City Council previously voted unanimously to overturn the hearings officer's earlier approval.

Timeline

  1. Last spring: The hearings officer's first approval was overturned by City Council.

  2. July: The city and PGE announced a settlement agreement.

  3. Nov. 21: The hearings officer approved the revised land use application.

  4. Wednesday, Dec. 2, 7 p.m.: The Forest Park Neighborhood Association and Forest Park Conservancy meet to discuss the decision and appeal.

  5. Friday, Dec. 4: Deadline for appeals.

Season Trajectory

The renewed approval follows City Council's unanimous vote last spring to overturn the first hearings officer decision on the Harborton project. Whether the revised settlement survives another round of appeals will shape how Portland balances transmission reliability against protections for Forest Park.

Residents near Forest Park could see new power poles and transmission lines near Highway 30 if the project proceeds. Ratepayers and neighbors should watch the appeal deadline and City Council action, since the approval is still contested.

The takeaway

Portland's handling of the Harborton project shows that reliability upgrades in protected green space can be reopened long after an initial approval. Residents who want a say should track the December appeal deadline.

What happens next

Appeals are due by Friday, Dec. 4, and the Forest Park Neighborhood Association and Forest Park Conservancy meet Wednesday, Dec. 2 at 7 p.m. to discuss the decision and next steps.

Further reading

Follow the latest decisions in Portland City Hall as the appeal deadline approaches.

Source note: This article includes information reported by Kgw.