Hearings Officer Approves Forest Park Tree Removal

Portland General Electric's revised transmission upgrade plan, which removes more than 370 trees, won approval from a city hearings officer.

Updated on Nov. 21, 2026 in Politics

Wide view of a dense conifer forest with a straight clearing cut through it, where a row of steel lattice transmission towers runs under overcast sky.
Portland General Electric's revised transmission project, which clears more than 370 trees from about five acres of Forest Park, won approval from a city hearings officer. AI Illustration. Upload story photo >

Live Poll

Should Portland approve utility projects that cut hundreds of trees to prevent outages?

A Portland hearings officer approved Portland General Electric's revised proposal to cut down more than 370 trees in Forest Park. The project covers about 5 acres of the 5,200-acre park and upgrades transmission lines.

Why it matters

The transmission work is needed to prevent potential power outages in North and Northwest Portland as electricity demand grows. The approval could be appealed to the Portland City Council, which rejected the project in 2025.

The decision rests on a hearings officer's review of a revised application, with mitigation funding raised from the original promise by $3.1 million to $5.5 million. It is not yet known whether the approval will be appealed to the City Council before the Dec. 4 deadline.

The players

Portland General Electric

Portland General Electric is the investor-owned utility that serves customers across much of Oregon, including the Portland metropolitan area.

Marisha Childs

Marisha Childs is a Portland city official whose role in the transmission project and related proceedings is part of the city's review process.

The details

Portland General Electric plans to rewire an existing 1970s transmission line and add a second line within its current right-of-way. A mediation agreement between the city and the utility, with three nonprofits participating, requires a large portion of the mitigation money to be spent within the project area, and the hearings officer required pre-construction wildlife surveys and timing restrictions to protect amphibians. Some environmental groups called the agreement a "backroom deal" because they were excluded from the final round of negotiations.

Timeline

  1. June 2025: A hearings officer approved PGE's original plan.

  2. 2025: The City Council rejected the transmission project.

  3. More than four months before the approval: The city and utility reached a mediation agreement.

  4. Friday, Nov. 20, 2026: The hearings officer approved the revised proposal.

  5. Dec. 4: Deadline to appeal the approval to the City Council.

Political Context

The hearings officer's approval reverses the City Council's 2025 rejection of this same transmission project, setting up a possible second round of review before the council. Environmental groups' objections to the mediation process mirror the broader tension between utility infrastructure needs and protection of the city's largest urban forest.

Residents in North and Northwest Portland could see fewer power outages once the transmission upgrade is complete, but the work will remove more than 370 trees. Anyone who uses the trails near the 5-acre project area may face changes during construction.

The takeaway

Large infrastructure projects in protected green space often hinge on how mitigation money is spent and who gets a seat at the negotiating table. Following the appeal deadline will show whether the city council revisits a decision it already rejected once.

What happens next

The Forest Park Conservancy has until Dec. 4 to appeal the hearings officer's approval to the Portland City Council.

Further reading

Follow more local decisions on the City Hall beat for context on how Portland's council and hearings process handles contested projects.

Source note: This article includes information reported by Oregon Live.