Metroparks Ends Cleveland Milling Deal After Developer Exit

Cleveland Metroparks has terminated its agreement for the Grain Craft mill redevelopment after the developer withdrew from the project.

Updated on Nov. 19, 2026 in Commercial

Weathered grain silos and a brick mill building stand above a calm river bank under overcast daylight, marking Cleveland's idle Merwin Avenue industrial riverfront.
Cleveland Metroparks terminated its redevelopment agreement for the Merwin Avenue mill site on September 16, 2026, after developer CLD withdrew, and will sell the properties by sealed bid. AI Illustration. Upload story photo >

Cleveland Metroparks terminated its memorandum of understanding for the Cleveland Milling Company redevelopment after CLD notified the agency on September 16, 2026, that it was withdrawing. The agency has authorized a sealed bid process to sell the former Grain Craft mill properties and Catanese properties.

Why it matters

The collapse leaves a long-planned riverfront redevelopment on Merwin Avenue without a developer and shifts the properties toward a fee sale to a new owner. The outcome affects the future use of a Cleveland industrial site and the public access that Metroparks intends to preserve.

The redevelopment's $61.6 million budget was backed by $10.3 million in federal historic tax credits and $5 million in state credits, while Metroparks paid $3.5 million and $4 million for the two property groups. How the sealed bid process will affect the public's share of these investments remains undetermined.

The players

Cleveland Metroparks

The regional park district that owns the Columbus Road Peninsula properties and oversees public riverfront access along the Cuyahoga River.

Ceres Enterprises

The development firm selected alongside LaPine Development LLC to redevelop the Grain Craft mill through Metroparks' 2025 request for proposals.

LaPine Development LLC

The development company that was selected with Ceres Enterprises to lead the Cleveland Milling Company redevelopment.

The details

CLD told Metroparks on September 16, 2026, that it was leaving the project, and the agency then provided formal notice ending the MOU. Metroparks staff recommends a fee sale of the properties while retaining a trail easement to keep public riverfront access, and demolition of the former Catanese buildings at 1600 Merwin Ave. has already begun.

Timeline

  1. 2025: Metroparks selected Ceres Enterprises and LaPine Development LLC through a request for proposals.

  2. December 2025: Federal historic tax credits totaling $10.3 million were secured.

  3. September 16, 2026: CLD notified Metroparks it was withdrawing from the project.

  4. November 19, 2026: The Metroparks board authorized a sealed bid process for the mill property.

Commercial Real Estate Context

The termination follows Metroparks' 2025 request for proposals that chose Ceres Enterprises and LaPine Development LLC to redevelop the Grain Craft mill, and the agency now reverts to a sealed bid sale of the same properties. The change returns the site to a fee sale rather than a public-private redevelopment.

Visitors to the Columbus Road Peninsula will keep public riverfront access through a retained trail easement even as the mill properties move to a new owner. Nearby residents may see changes to the Merwin Avenue corridor depending on how the buyer redevelops the site.

The takeaway

A failed redevelopment does not always end a site's future, since public access and a new sale can still shape what comes next on the Cuyahoga River.

What happens next

A sealed bid process for the former mill and Catanese properties is expected to proceed, with the bid outcome and the future of the Brownfield funds still to be determined.