Cleveland Approved $17.9 Million in Solar Contracts

The city moved forward with two landfill-based solar projects to boost local renewable energy production.

Updated on Oct. 8, 2026 in Utilities

Isometric editorial illustration featuring rows of solar panels neatly arranged across a reclaimed industrial plot of land.
The Cleveland Board of Control approved $17.9 million in contracts on June 3, 2026, to install solar energy arrays on two former landfill sites. AI Illustration. Upload story photo >

Live Poll

Should your local government convert former landfill sites into renewable energy installations?

On June 3, 2026, the Cleveland Board of Control approved $17.9 million in contracts for new solar energy installations. These projects aim to repurpose former landfill sites for electricity generation.

Why it matters

The initiative leverages federal subgrants and elective tax credits to transform disused municipal land into productive assets. This strategy helps the city lower long-term energy costs while promoting sustainable infrastructure.

The city approved contracts worth $17.9 million, supported by a $14,882,505 federal subgrant from Cuyahoga County. These solar installations are expected to generate between 7 and 9 megawatts of power.

The players

Enerlogics Networks Inc.

This firm holds the primary contracts for the development and construction of the city's new solar projects.

Cuyahoga County

The county government provided the authorized federal subgrant of $14.8 million to support the renewable energy initiatives.

The details

The project will install solar arrays at the West 11th Street/Spring Road landfill and the Kolthoff Drive landfill. Enerlogics Networks Inc., working alongside Energy Independent Solutions, LLC and Prairie Wind Group, LLC, will manage the design and construction efforts.

Timeline

  1. The Board of Control approved the solar contracts on June 3, 2026.

  2. A physical-work-test deadline to qualify for tax credits is July 4, 2026.

  3. Construction on the sites is expected to begin before the end of 2026.

  4. The solar projects have an in-service deadline of December 31, 2027.

Market Landscape

This development follows the trend of municipalities utilizing the Inflation Reduction Act's elective pay provisions to monetize clean energy projects. It positions Cleveland to capture significant federal tax credits while reclaiming legacy industrial sites for public utility.

Residents and local utility customers stand to benefit from increased clean energy capacity and the effective use of federal grants to offset municipal project costs. These developments aim to improve the city's energy portfolio without placing the entire financial burden on local taxpayers.

The takeaway

Repurposing former landfills into solar arrays serves as a sustainable model for cities looking to upgrade infrastructure. Leveraging federal funding for such projects remains a critical component for modern urban energy planning.

Further reading

Learn more about local infrastructure projects in the Utilities section.

Source note: This article includes information reported by Cleveland.

Live Poll

Should your local government convert former landfill sites into renewable energy installations?