Holtec Restructuring Shifts Indian Point Decommissioning Liabilities
Holtec International seeks New York regulatory approval to move decommissioning assets and liabilities to an affiliate known as DEAMCO.
Updated on Nov. 12, 2026 in Nuclear

Live Poll
Do you trust Holtec to finish Indian Point's cleanup without sticking taxpayers with the bill?
Holtec International, which owns the former Indian Point nuclear power plant, has proposed a corporate restructuring that transfers certain decommissioning assets and liabilities to an affiliate called DEAMCO. The plan requires approval from the New York State Public Service Commission and has already been reviewed and approved by the Nuclear Regulatory Commission.
Why it matters
Critics say the restructuring limits liability for decommissioning costs, while Westchester County Executive Ken Jenkins has urged state regulators to reject it unless additional protections are added. The outcome will determine who ultimately bears responsibility for finishing the Indian Point site's cleanup in New York.
The proposal substitutes DEAMCO as the upstream owner of HIP2, LLC and HIP3, LLC, replacing NAMCO in that ownership chain. Decommissioning is funded by trust funds transferred from Entergy to Holtec, but the extraction contains no exact fund balances or cost estimates.
The players
Holtec International
Holtec International is a nuclear technology company that owns the former Indian Point plant and is overseeing its decommissioning.
Public Service Commission of New York
The New York State Public Service Commission is the state regulator that must approve the proposed restructuring before it can take effect.
The details
Holtec would continue providing decommissioning services under the restructuring, and it says it is hiring an independent fiduciary manager and adding independent oversight of how trust fund money is used. Riverkeeper staff attorney Larissa Liebmann criticized the plan for limiting liability, while Buchanan Mayor Theresa Knickerbocker said the trust funds are sufficient to finish the work.
Timeline
The next Indian Point Decommissioning Oversight Board meeting is scheduled for Dec. 10.
Deeper Dive
The restructuring has already cleared the Nuclear Regulatory Commission, leaving the New York Public Service Commission as the final gatekeeper for how Indian Point's decommissioning money and liability are handled. That state-level review is the remaining checkpoint in the plant's cleanup.
Residents in Westchester County and surrounding communities have a stake in whether decommissioning money and liability remain secure through the cleanup. The state's decision will determine whether added protections are required before the restructuring proceeds.
The takeaway
Decommissioning a nuclear plant depends as much on who holds the money and the liability as on the cleanup work itself. Watching the state's review of trust fund oversight will show whether those safeguards hold up.
What happens next
The next Indian Point Decommissioning Oversight Board meeting is scheduled for Dec. 10.
Further reading
For more on the nuclear industry's cleanup and regulatory issues, see Nuclear coverage.