Athletics to Install Final Stadium Roof Trusses by 2026
Construction crews are set to complete the five-arch roof structure for the new $2.1 billion Las Vegas ballpark.
Updated on Oct. 23, 2026 in Baseball

Live Poll
Do you believe large-scale stadium projects provide sufficient long-term value to your community?
The Las Vegas ballpark construction project will see the installation of its final two roof trusses by the end of 2026. This milestone marks significant progress toward the planned completion of the $2.1 billion facility.
Why it matters
The structural completion of the stadium roof is a critical step in finalizing the exterior envelope of the project. These efforts ensure the venue remains on schedule for its projected total enclosure in August 2027.
The stadium design features five steel truss arches, with three already secured in place. The total project investment for the facility stands at $2.1 billion.
The players
Athletics
The Athletics are a Major League Baseball franchise currently in the process of transitioning to a new home in Las Vegas.
The details
Crews are currently installing tri-chord trusses as connectors between the arches to stabilize the framework. The final truss is designed to support a specialized cable net glass wall that provides views of the Las Vegas Strip.
Timeline
This week marks the removal of the first shoring tower.
The fourth roof truss installation will conclude during the first two weeks of November 2026.
Five shoring towers will be removed around Thanksgiving 2026.
The final two roof trusses will be installed by the end of 2026.
The ballpark facility will be fully enclosed in August 2027.
Season Trajectory
The roof installation marks a critical phase in the long-term infrastructure development for the Athletics' new home. This progress aligns the project with the established timeline for the 2027 ballpark enclosure goal.
The completion of the roof structure signifies that the exterior shell of the stadium is nearing its finished state. This pace of work determines the remaining timeline for interior fit-out and eventual public access to the Las Vegas Strip venue.
The takeaway
The installation of the final roof arches confirms that the stadium frame is advancing toward full enclosure. Residents and visitors should monitor construction updates for any potential road impacts around the site as the shoring towers are removed.
Further reading
For more updates on professional sports infrastructure, visit Baseball.
Source note: This article includes information reported by Las Vegas Review-Journal.